Question: 181. Which PRINCE2 7 practice establishes whether a project continues to be worthwhile?
- Quality
2. Business Case
3. Progress
4. Issues
Correct Answer: 2. Business Case
Explanation:
The Business Case practice focuses on establishing whether the project remains desirable, viable, and achievable. It provides the basis for deciding whether the expected benefits justify the investment of resources, considering factors such as costs, risks, outcomes, and benefits. The Business Case should not be treated as a document created once and then ignored. It is reviewed and updated as the project develops and circumstances change. This supports the PRINCE2 principle of ensuring continued business justification and gives decision-makers relevant information at important points throughout the project.
Question: 182. Which Project Board member represents the interests of those responsible for supplying specialist products and services?
- Executive
2. Senior User
3. Senior Supplier
4. Project Manager
Correct Answer: 3. Senior Supplier
Explanation:
The Senior Supplier represents the interests of those designing, developing, procuring, or supplying the project’s specialist products. This role provides the Project Board with appropriate supplier and technical perspectives and helps ensure that the proposed solutions are realistic from a delivery standpoint. The Senior Supplier works alongside the Executive and Senior User on the Project Board. The Executive represents business interests, while the Senior User represents user interests. These three perspectives help the Project Board maintain balanced governance and make informed decisions about the project.
Question: 183. What is the main purpose of a Stage Plan?
- To define the detailed management arrangements for a management stage
2. To authorize the entire project before initiation
3. To describe the organization’s complete portfolio
4. To record all stakeholder communications after closure
Correct Answer: 1. To define the detailed management arrangements for a management stage
Explanation:
A Stage Plan provides the detailed plan for a particular management stage. It describes what is expected to be delivered, how and when work will be performed, the resources required, controls, and other relevant management information. It is used by the Project Manager to manage the stage within the agreed tolerances. The Project Plan provides a higher-level view of the overall project, while the Stage Plan provides more detailed planning for the current stage. Planning in this way supports progressive elaboration and effective control.
Question: 184. A stakeholder requests a modification to an approved product requirement. How should this initially be treated?
- As a lesson
2. As a risk response
3. As a request for change
4. As a Checkpoint Report
Correct Answer: 3. As a request for change
Explanation:
A request to modify an approved product requirement is normally treated as a request for change, which is a type of issue. The proposed change should be recorded and assessed according to the project’s issue and change-control arrangements. The assessment should consider factors such as impact on scope, cost, time, quality, risk, benefits, and tolerances. The appropriate authority then decides whether the change should be approved, rejected, or handled through another agreed route. This prevents unauthorized changes from being introduced into approved project baselines.
Question: 185. Which PRINCE2 7 principle supports delegation of authority within agreed limits?
- Focus on products
2. Manage by exception
3. Learn from experience
4. Manage by stages
Correct Answer: 2. Manage by exception
Explanation:
Manage by exception establishes clear tolerances and allows authority to be delegated within those limits. For example, the Project Board can delegate authority to the Project Manager to manage a stage within agreed time, cost, scope, quality, risk, and benefits tolerances. If the Project Manager forecasts that these limits will be exceeded, the matter is escalated to the appropriate decision-maker. This reduces unnecessary involvement by senior management in routine decisions while maintaining effective control. The principle therefore combines delegation with clear accountability and escalation arrangements.
Question: 186. Which statement best describes a Project Brief?
- It is the final report produced after project closure
2. It provides the information needed to decide whether the project should be initiated
3. It is a detailed description of every specialist product
4. It replaces the Business Case throughout the project
Correct Answer: 2. It provides the information needed to decide whether the project should be initiated
Explanation:
The Project Brief provides an early definition of the project and establishes enough information for the Project Board to decide whether it should be initiated. It can include the project’s background, objectives, desired outcomes, scope, key products, project approach, initial Business Case information, and proposed management arrangements. It is developed during Starting up a Project and provides a foundation for more detailed initiation work. The Project Brief should not be confused with the Project Initiation Documentation, which provides the more complete baseline for managing the project.
Question: 187. Which report gives the Project Board regular information about progress during a management stage?
- Checkpoint Report
2. Highlight Report
3. Lessons Report
4. End Project Report
Correct Answer: 2. Highlight Report
Explanation:
A Highlight Report provides the Project Board with regular information about the progress of a management stage. It is produced by the Project Manager at agreed intervals and can cover progress against plans, forecasts, risks, issues, tolerances, and other significant information. Its purpose is to give the Project Board sufficient visibility without requiring involvement in day-to-day management. A Checkpoint Report serves a different purpose by providing information from a Team Manager to the Project Manager about a Work Package. The distinction supports efficient communication at different management levels.
Question: 188. What is a key purpose of the Quality Register?
- To record quality-related activities and their results
2. To authorize changes to the Business Case
3. To define the project’s financial investment
4. To replace all Product Descriptions
Correct Answer: 1. To record quality-related activities and their results
Explanation:
The Quality Register provides a record of planned and completed quality activities and their results. It can help the project track reviews, inspections, testing, and other quality-control activities associated with products. Maintaining this information supports transparency and allows the project to demonstrate that appropriate quality controls have been performed. The Quality Register does not replace Product Descriptions or define the project’s financial justification. Instead, it acts as a management record that helps monitor whether planned quality activities are being carried out and whether their outcomes are satisfactory.
Question: 189. What should a Project Manager do when a risk becomes an actual event that requires immediate management?
- Continue treating it only as a potential future risk
2. Ignore it until the next stage boundary
3. Treat the resulting situation as an issue and manage it appropriately
4. Automatically close the project
Correct Answer: 3. Treat the resulting situation as an issue and manage it appropriately
Explanation:
A risk represents uncertainty about a possible future event, whereas an issue is something that has already occurred or requires a decision or response. When a risk materializes, the resulting situation should be managed as an issue where appropriate. The project should assess its impact and apply the relevant issue-management and escalation arrangements. The original risk record may also need to be updated to reflect what happened and what was learned. This distinction helps ensure that actual problems receive active management rather than continuing to be treated as hypothetical possibilities.
Question: 190. Which process is primarily concerned with preparing the information needed to decide what should happen at the end of a management stage?
- Managing a Stage Boundary
2. Starting up a Project
3. Managing Product Delivery
4. Closing a Project
Correct Answer: 1. Managing a Stage Boundary
Explanation:
Managing a Stage Boundary prepares the information required for the Project Board to make a decision about the next stage. The Project Manager reviews the completed stage, updates relevant project information, confirms the continued business justification, and prepares the next Stage Plan where appropriate. The process provides a controlled transition between management stages. It allows the Project Board to assess current performance and future plans before authorizing additional work. This supports the manage-by-stages principle and prevents the project from automatically progressing without an informed decision.
Question: 191. Which document defines how the project will control and manage issues?
- Risk Management Approach
2. Issue Management Approach
3. Benefits Management Approach
4. Communication Management Approach
Correct Answer: 2. Issue Management Approach
Explanation:
The Issue Management Approach defines how issues will be captured, assessed, controlled, and managed within the project. It can establish responsibilities, procedures, categories, thresholds, reporting arrangements, and decision-making routes. This helps ensure that requests for change, off-specifications, and other issues are handled consistently. The approach should be tailored to the project’s circumstances and aligned with organizational requirements. It is distinct from the Risk Management Approach, which addresses uncertainty, and from the Communication Management Approach, which focuses on how project information is communicated to stakeholders.
Question: 192. Why is product-based planning important in PRINCE2?
- It ensures that only financial activities are planned
2. It focuses planning on the products that must be created and their required quality
3. It removes the need to identify dependencies
4. It prevents changes to approved products
Correct Answer: 2. It focuses planning on the products that must be created and their required quality
Explanation:
Product-based planning starts by identifying the products that the project or stage must deliver and then considers the activities and resources required to create them. This helps ensure that planning is driven by clearly defined outputs rather than simply listing activities. Product-based planning can involve identifying the required products, defining their characteristics, understanding product dependencies, and determining the work needed to create them. This approach supports the Focus on Products principle and makes acceptance and quality expectations clearer throughout the project.
Question: 193. What is the purpose of the End Stage Report?
- To provide a detailed plan for the entire organization
2. To summarize the performance of the completed stage for the Project Board
3. To replace the next Stage Plan
4. To authorize individual Work Packages
Correct Answer: 2. To summarize the performance of the completed stage for the Project Board
Explanation:
The End Stage Report provides the Project Board with information about how the completed stage performed compared with its approved plans and tolerances. It can summarize actual progress, costs, quality performance, risks, issues, products delivered, and other relevant information. The report supports the Project Board’s assessment of the completed stage and its decision about the project’s continuation. It is different from the End Project Report, which covers the performance and results of the entire project at closure.
Question: 194. Which approach should be used to determine how sustainability should be addressed within a project?
- Sustainability management arrangements appropriate to the project
2. Only the supplier’s environmental preferences
3. A fixed approach that is identical for every project
4. No defined approach unless a problem occurs
Correct Answer: 1. Sustainability management arrangements appropriate to the project
Explanation:
PRINCE2 7 recognizes sustainability as an important consideration that should be addressed according to the project’s context. Sustainability may influence project objectives, product requirements, delivery methods, resource use, organizational policies, and expected outcomes. The project’s sustainability considerations should be defined and managed in a way that is appropriate to its circumstances and organizational environment. This does not mean applying identical sustainability controls to every project. Instead, the project should determine relevant sustainability objectives, measures, responsibilities, and controls through appropriate management arrangements.
Question: 195. Which action best demonstrates the Focus on Products principle?
- Starting activities before defining expected outputs
2. Measuring progress only by hours worked
3. Clearly defining products and their acceptance criteria before planning the work
4. Allowing each team to define products after delivery
Correct Answer: 3. Clearly defining products and their acceptance criteria before planning the work
Explanation:
Focus on Products means that the project should clearly understand what products must be delivered and what quality requirements they must satisfy. Defining products and acceptance criteria before detailed work is planned helps establish a shared understanding of the required outputs. It also supports product-based planning because activities can then be identified based on what is needed to create the products. Simply measuring effort or hours worked does not demonstrate whether the required outputs are being achieved. Product focus therefore connects planning, quality, acceptance, and delivery.
Question: 196. Who normally has authority to direct the project at the Project Board level?
- Project Support
2. Team Manager
3. Project Board
4. Individual supplier
Correct Answer: 3. Project Board
Explanation:
The Project Board provides overall direction and governance for the project through the Directing a Project process. It represents business, user, and supplier interests and makes key decisions within its authority. The Project Manager is responsible for day-to-day management within the authority delegated by the Project Board. Team Managers and suppliers are responsible for delivering assigned work within their agreed responsibilities. This separation prevents the Project Board from becoming involved in routine operational management while retaining appropriate strategic control and decision-making authority.
Question: 197. What is the main reason for establishing tolerances for a project or stage?
- To define the limits within which delegated management authority can operate
2. To guarantee that no changes will ever occur
3. To eliminate the need for reporting
4. To prevent the Project Manager from making decisions
Correct Answer: 1. To define the limits within which delegated management authority can operate
Explanation:
Tolerances define permissible limits for areas such as time, cost, scope, quality, risk, and benefits. Within those limits, the person with delegated authority can manage without referring every decision to a higher level. If the forecast indicates that an agreed tolerance will be exceeded, the matter should be escalated according to the project’s governance arrangements. This is a central part of managing by exception. Tolerances therefore provide both flexibility and control: managers have room to manage while senior decision-makers are informed when significant deviations require attention.
Question: 198. Which activity is associated with Closing a Project?
- Creating the initial Project Brief
2. Authorizing the first management stage
3. Confirming acceptance of the project’s products and evaluating project performance
4. Creating the first Work Package
Correct Answer: 3. Confirming acceptance of the project’s products and evaluating project performance
Explanation:
Closing a Project includes activities needed to bring the project to a controlled conclusion. These can include confirming product acceptance, reviewing whether project objectives and expected outcomes have been achieved, assessing project performance, capturing lessons, and confirming follow-on actions such as benefits reviews where appropriate. The process also supports the preparation of information for the Project Board’s closure decision. This differs from Starting up a Project, which establishes whether the project is worthwhile and feasible, and from Managing Product Delivery, which focuses on delivering products during the project.
Question: 199. What is the purpose of the Benefits Management Approach?
- To describe how expected benefits will be managed, measured, and reviewed
2. To define every supplier’s technical specification
3. To record only project risks
4. To replace the Project Plan
Correct Answer: 1. To describe how expected benefits will be managed, measured, and reviewed
Explanation:
The Benefits Management Approach describes how expected benefits will be managed and assessed. It can establish responsibilities, measurement methods, timing, review arrangements, and the relationship between project outputs, outcomes, and expected benefits. Some benefits may only become measurable after products have been delivered and the project has closed, so benefits management can extend beyond project closure. The approach helps ensure that benefits are not merely listed as aspirations but are given appropriate consideration, ownership, measurement, and review throughout the relevant period.
Question: 200. Which statement best describes the PRINCE2 7 principle of Learn from Experience?
- Lessons should only be documented after project closure
2. Lessons should be identified, recorded, and applied throughout the project
3. Lessons are only relevant when a project fails
4. Lessons should be handled exclusively by external suppliers
Correct Answer: 2. Lessons should be identified, recorded, and applied throughout the project
Explanation:
Learn from Experience requires projects to actively use knowledge from previous and current work. Lessons can come from earlier projects, organizational experience, external sources, or events occurring during the current project. They should be identified, captured, and considered when relevant so that the project can improve its approach while work is still underway. Waiting until closure can mean missing opportunities to prevent repeated problems or improve current delivery. The principle therefore encourages continuous learning rather than treating lessons as a final administrative exercise.