Question 201. A project manager is reviewing the approved scope baseline to determine exactly what work is included in the project. Which components make up the scope baseline?
- Risk register, schedule, and cost forecast
- Requirements log, team charter, and procurement plan
- Scope statement, WBS, and WBS dictionary
- Project charter, stakeholder register, and issue log
Correct Answer: 3. Scope statement, WBS, and WBS dictionary
Explanation:
The scope baseline is composed of the approved project scope statement, work breakdown structure (WBS), and WBS dictionary. Together, these components define the project’s approved scope and provide a structured basis for planning, executing, and controlling the work. The scope statement describes what the project will and will not deliver, the WBS decomposes the total project scope into manageable components, and the WBS dictionary provides detailed information about WBS elements. Other project documents, such as the risk register and stakeholder register, support project management but are not components of the scope baseline.
Question 202. A project team is breaking a large deliverable into progressively smaller components until the work can be estimated, scheduled, and assigned. What technique is being used?
- Forecasting
- Decomposition
- Benchmarking
- Trend analysis
Correct Answer: 2. Decomposition
Explanation:
Decomposition is the technique of dividing project scope and deliverables into smaller, more manageable components. In scope management, decomposition continues until the work is detailed enough to support reliable planning, estimating, scheduling, assigning responsibility, and controlling performance. The resulting structure is represented through the work breakdown structure. Decomposition does not mean simply dividing work arbitrarily; the team should ensure that the resulting components collectively represent the required project scope. Benchmarking compares practices or performance, trend analysis examines patterns over time, and forecasting uses available information to predict future conditions.
Question 203. A project manager discovers that the team has added extra features to a product because they believed the customer would appreciate them, even though the features were not requested or approved. What project management problem has occurred?
- Rolling wave planning
- Gold plating
- Scope validation
- Progressive elaboration
Correct Answer: 2. Gold plating
Explanation:
Gold plating occurs when the project team adds extra features, functionality, or work that was not included in the approved requirements or scope, often with the intention of providing additional value. Although the added features may appear beneficial, unauthorized work can increase cost, schedule, complexity, quality risks, and support requirements. Project teams should deliver the approved scope rather than independently adding enhancements. If a customer wants additional functionality, the request should be evaluated through the appropriate requirements and change control processes. Gold plating is therefore different from legitimate scope refinement or approved changes.
Question 204. A project manager notices that an activity can start two days before its predecessor is fully completed because the remaining predecessor work does not affect the successor’s initial work. What scheduling concept can be used?
- Float
- Lead
- Lag
- Milestone
Correct Answer: 2. Lead
Explanation:
A lead allows a successor activity to begin before the predecessor activity has completely finished. In the scenario, the successor can start two days before completion of the predecessor because the remaining predecessor work does not prevent the successor from beginning. A lead can help shorten a schedule when activities can safely overlap. A lag introduces a waiting period between activities, while float represents the amount of schedule flexibility an activity may have without affecting specified schedule constraints. A milestone is a significant event or point in the project and normally has zero duration.
Question 205. A project manager determines that a planned activity cannot begin until five days after its predecessor is completed because equipment must be transported to the work location. What scheduling concept is being applied?
- Fast tracking
- Lag
- Lead
- Crashing
Correct Answer: 2. Lag
Explanation:
A lag is an intentional waiting period between activities. In this scenario, the successor activity must wait five days after the predecessor finishes because equipment needs to be transported to the work location. The waiting period represents lag in the relationship between the activities. A lead would allow the successor to begin before the predecessor is finished. Crashing attempts to shorten activity duration by adding resources or increasing expenditure, while fast tracking involves overlapping activities that were originally planned sequentially. Lag should be represented appropriately in the project schedule so the timing reflects actual project conditions.
Question 206. A project manager is reviewing an estimate and wants to understand the amount of money required to complete all remaining project work. Which measure should be examined?
- Planned Value
- Estimate to Complete
- Variance at Completion
- Budget at Completion
Correct Answer: 2. Estimate to Complete
Explanation:
Estimate to Complete (ETC) represents the expected cost required to finish all remaining authorized project work. It is a forward-looking measure and can be calculated using different forecasting methods depending on whether current cost performance is expected to continue. Budget at Completion represents the total approved project budget, while Planned Value represents the budgeted value of work scheduled by a specific point in time. Variance at Completion compares the approved budget with the forecasted total cost at completion. Therefore, when the question focuses specifically on the cost needed to finish the remaining work, ETC is the appropriate measure.
Question 207. A project team has completed a deliverable and wants to determine whether it meets the documented quality requirements before presenting it to the customer for formal acceptance. Which activity is most appropriate?
- Manage Stakeholder Engagement
- Control Scope
- Control Quality
- Validate Scope
Correct Answer: 3. Control Quality
Explanation:
Control Quality involves monitoring and measuring project results to determine whether they comply with relevant quality requirements and identifying ways to eliminate causes of unsatisfactory results. The team may use inspections, testing, measurements, or other quality-control techniques to evaluate the deliverable. Validate Scope focuses on formal acceptance of completed deliverables by the customer or sponsor. A deliverable can therefore undergo quality control before it is presented for formal scope validation. Control Scope manages changes to project scope, while Manage Stakeholder Engagement focuses on stakeholder communication and involvement.
Question 208. A project manager wants to ensure that the project team understands the conditions under which a completed deliverable will be accepted by the customer. Where should these conditions be documented?
- Acceptance criteria
- Resource calendar
- Risk register
- Issue log
Correct Answer: 1. Acceptance criteria
Explanation:
Acceptance criteria define the specific conditions, requirements, standards, or other conditions that must be satisfied before a deliverable can be accepted. Clear acceptance criteria help the project team understand what constitutes an acceptable result and provide a basis for validating completed deliverables. They can include functional requirements, performance expectations, quality standards, regulatory conditions, or other agreed conditions. The risk register documents risks, the issue log records current problems, and the resource calendar describes resource availability. Acceptance criteria therefore provide the appropriate basis for determining whether a deliverable meets the agreed expectations.
Question 209. A project manager is working with stakeholders who have conflicting priorities. The project manager brings them together to negotiate a solution that balances their interests while maintaining project objectives. Which skill is most directly being applied?
- Auditing
- Negotiation
- Estimating
- Decomposition
Correct Answer: 2. Negotiation
Explanation:
Negotiation involves working with parties who have different interests, expectations, or priorities to reach an acceptable agreement. Project managers frequently use negotiation when dealing with stakeholders, resources, suppliers, schedules, requirements, budgets, and competing project needs. Effective negotiation involves understanding the interests of the parties, communicating clearly, exploring alternatives, and seeking an agreement consistent with project objectives and organizational constraints. Decomposition concerns breaking scope into smaller components, estimating concerns determining expected cost or effort, and auditing evaluates compliance or process effectiveness. In this scenario, balancing conflicting stakeholder priorities directly requires negotiation.
Question 210. A project manager discovers that a previously identified risk has occurred and is now affecting project work. What should the project manager do?
- Continue monitoring it only as a future possibility
- Treat it as an active issue and implement the appropriate response
- Ignore it because the risk register is already approved
- Remove it from all project records
Correct Answer: 2. Treat it as an active issue and implement the appropriate response
Explanation:
When a risk event occurs, the uncertainty associated with that event has materialized and it becomes an issue requiring management. The project manager should follow the planned risk response when appropriate, assess the actual impact, update project documentation, and manage the resulting issue. Simply continuing to monitor the event as though it were only a future possibility would not address its actual effects. The risk register and issue log may both require updates depending on the project’s procedures. Effective risk management includes responding to risks when they occur and managing their consequences.
Question 211. A project manager is preparing the project schedule and identifies an activity that has no flexibility because delaying it would directly delay the project completion date. What does this indicate?
- The activity is an external dependency
- The activity is on the critical path
- The activity has maximum float
- The activity is a milestone
Correct Answer: 2. The activity is on the critical path
Explanation:
An activity on the critical path has little or no total float under the schedule’s current assumptions, and delaying it can delay the project’s planned completion date. Critical path analysis helps the project team identify the sequence of activities that determines the minimum possible project duration. The critical path can change as the project progresses if activity durations, dependencies, or constraints change. A milestone is a significant event rather than a normal work activity, and an external dependency describes a relationship influenced by factors outside the project team. Maximum float would represent the opposite of having no schedule flexibility.
Question 212. A project manager is evaluating the likely total cost of a project based on current performance and expects the existing cost efficiency to continue. Which forecasting measure should be calculated?
- Cost Variance
- Estimate at Completion
- Planned Value
- Schedule Variance
Correct Answer: 2. Estimate at Completion
Explanation:
Estimate at Completion (EAC) is a forecast of the expected total cost of the project when all authorized work is completed. When current cost performance is expected to continue, EAC can be calculated using an appropriate earned value forecasting formula, depending on the assumptions about future performance. EAC provides management with information about the likely final project cost. Planned Value describes the budgeted value of scheduled work, while Cost Variance measures the difference between earned value and actual cost. Schedule Variance focuses on schedule performance. EAC is therefore the appropriate measure for forecasting the project’s expected final cost.
Question 213. A project manager wants to ensure that team members understand how they will communicate, make decisions, resolve conflicts, and work together. Which document should be developed?
- Requirements traceability matrix
- Team charter
- Risk register
- Procurement statement of work
Correct Answer: 2. Team charter
Explanation:
A team charter establishes guidelines for how project team members will work together. It can define team values, communication expectations, decision-making approaches, conflict-management methods, meeting practices, and other working agreements. Developing the charter collaboratively can increase shared understanding and commitment among team members. A risk register records project risks, a procurement statement of work describes work or requirements for a procurement, and a requirements traceability matrix links requirements to related project elements. The team charter is therefore the appropriate document for establishing expectations about team collaboration and behavior.
Question 214. A project manager is preparing a cost estimate and wants to use historical information from a similar previous project, adjusting for known differences. Which estimating technique is being used?
- Parametric estimating
- Analogous estimating
- Bottom-up estimating
- Three-point estimating
Correct Answer: 2. Analogous estimating
Explanation:
Analogous estimating uses the actual cost or duration of a previous, similar project or activity as the basis for estimating the current work. The estimate is adjusted when differences in complexity, size, technology, conditions, or other factors exist. Analogous estimating is generally faster and requires less detailed information than bottom-up estimating, although it may be less precise. Parametric estimating uses a statistical relationship between variables, while three-point estimating considers multiple estimates to address uncertainty. Bottom-up estimating develops estimates from detailed components and aggregates them into a total.
Question 215. A project team is uncertain whether a supplier will deliver a critical component on time. The project manager wants to reduce the threat by identifying an alternative supplier before the delay occurs. Which risk response is most appropriate?
- Share
- Mitigate
- Accept
- Exploit
Correct Answer: 2. Mitigate
Explanation:
Mitigation involves taking action to reduce the probability or impact of a threat to an acceptable level. Identifying an alternative supplier before a potential delivery failure occurs can reduce the impact of a supplier delay because the project has another source available. Risk acceptance would involve taking no proactive action beyond monitoring or preparing as appropriate. Exploit is an opportunity response designed to ensure a positive risk occurs, while share is generally used for opportunities by allocating ownership to a party better positioned to realize the benefit. Mitigation is therefore appropriate for reducing this supplier-related threat.
Question 216. A project manager is reviewing the project’s assumptions and constraints before finalizing the schedule. Why is this review important?
- They guarantee that the project will finish early
- They eliminate all project risks
- Assumptions and constraints can influence project planning and execution
- They automatically replace the project charter
Correct Answer: 3. Assumptions and constraints can influence project planning and execution
Explanation:
Assumptions are conditions believed to be true for planning purposes, while constraints are limitations that restrict available choices or flexibility. Both can significantly influence scope, schedule, cost, resources, quality, procurement, and risk decisions. Reviewing them helps the project team verify whether planning remains realistic and identify conditions that may require further analysis or updates. Assumptions may later prove incorrect and create risks, while constraints can limit possible approaches. Neither automatically replaces the project charter, eliminates all risks, nor guarantees early completion. Their value comes from explicitly recognizing conditions that affect how the project can be planned and executed.
Question 217. A project manager is reviewing whether a project activity can be delayed without delaying the planned project completion date. Which scheduling concept should be examined?
- Work package
- Lag
- Float
- Milestone
Correct Answer: 3. Float
Explanation:
Float, also called slack in some scheduling contexts, represents the amount of time an activity can be delayed without violating a specified schedule constraint. Total float is commonly associated with the amount of delay an activity can experience without delaying the project’s planned completion date or another defined constraint. Activities on the critical path typically have little or no total float. A milestone represents a significant event, a work package is a scope component, and lag represents a waiting period between related activities. Examining float helps the project manager understand schedule flexibility and identify activities requiring closer attention.
Question 218. A project manager is evaluating an adaptive project and notices that the team has completed a potentially usable product increment at the end of an iteration. What should the team use to determine whether the increment meets the agreed completion standard?
- Stakeholder register
- Definition of Done
- Procurement statement of work
- Risk register
Correct Answer: 2. Definition of Done
Explanation:
The Definition of Done is a shared set of criteria that describes the conditions a product increment must satisfy to be considered complete according to the team’s agreed working standards. It can include requirements related to development, testing, documentation, quality, integration, and other completion conditions. Using a common Definition of Done helps create transparency and a shared understanding of what completed work means. A risk register tracks risks, a procurement statement of work defines procurement requirements, and a stakeholder register provides stakeholder information. The Definition of Done is therefore the relevant reference for determining completion of an adaptive product increment.
Question 219. A project manager notices that a stakeholder’s influence has increased significantly because the stakeholder’s department will now operate the project’s final product. What should the project manager do?
- Transfer all project risks to the stakeholder
- Remove the stakeholder from project communications
- Update stakeholder information and adjust the engagement approach as needed
- Ignore the change because the stakeholder register was created during initiation
Correct Answer: 3. Update stakeholder information and adjust the engagement approach as needed
Explanation:
Stakeholder characteristics and levels of influence can change throughout a project. When a stakeholder becomes more influential because their organization will operate the final product, the project manager should reassess relevant stakeholder information and determine whether the engagement strategy needs adjustment. This may involve changing communication frequency, decision-making involvement, information needs, or relationship management activities. Stakeholder management is an ongoing process rather than a one-time activity completed during initiation. Removing the stakeholder or transferring risks would not address the underlying change in stakeholder influence or operational responsibility.
Question 220. A project manager has completed the final project activities and needs to preserve important project information for organizational use after closure. What should the project manager do?
- Keep the project formally open indefinitely
- Archive relevant project records according to organizational procedures
- Delete temporary and permanent records immediately
- Leave all project information with individual team members
Correct Answer: 2. Archive relevant project records according to organizational procedures
Explanation:
Project closure includes preserving relevant project information according to organizational policies and procedures. Important records may include approved documents, contracts, deliverable information, lessons learned, performance records, and other historical information that can support audits, future projects, or organizational learning. Archiving records helps ensure that valuable knowledge remains accessible after the project team is released. Deleting records or leaving information only with individual team members can result in lost knowledge and poor traceability. Keeping a project formally open indefinitely is also inconsistent with proper closure when the project’s objectives and closure criteria have been satisfied.