View Full CompTIA Project+ PK0-005 Exam Dumps and Practice Test Dumps
Question 201. What is the primary purpose of a project business case?
- To define individual employee performance reviews
- To justify the project by describing its expected value, costs, benefits, and risks
- To document every task that will be performed during execution
- To replace the project schedule after approval
Correct Answer: 2. To justify the project by describing its expected value, costs, benefits, and risks.
Explanation:
A business case provides the rationale for undertaking a project. It typically describes the business problem or opportunity, expected benefits, estimated costs, major risks, and alignment with organizational objectives. Decision-makers use this information to determine whether the proposed investment is reasonable and whether the project should receive authorization. A business case is not the same as a detailed project schedule because it focuses on justification rather than task-level execution. It also does not replace employee evaluations or project management artifacts. Once approved, the business case can provide continued context for decisions throughout the project and help stakeholders understand why the project is being funded.
Question 202. Which organizational structure gives the project manager the greatest authority over project resources?
- Functional
- Weak matrix
- Projectized
- Divisional
Correct Answer: 3. Projectized.
Explanation:
In a projectized organizational structure, the project manager generally has significant authority over project resources, priorities, schedules, and day-to-day project decisions. Team members are often assigned primarily or exclusively to projects, which makes coordination and resource control more direct. In a functional structure, authority normally remains with functional managers, while weak matrix structures give the project manager relatively limited authority. Organizational structures can influence communication, decision-making speed, resource availability, and reporting relationships. Understanding these differences is important for a project manager because the same project-management approach may need to be adapted depending on how much authority the project manager has within the organization.
Question 203. A project team needs to determine whether a project should be completed internally or obtained from an external supplier. What should the team perform?
- Make-or-buy analysis
- Stakeholder register review
- Quality audit
- Lessons learned review
Correct Answer: 1. Make-or-buy analysis.
Explanation:
A make-or-buy analysis helps an organization determine whether a product, service, or component should be developed internally or obtained from an external supplier. The analysis can consider cost, available skills, capacity, schedule requirements, quality considerations, security concerns, supplier capabilities, and strategic factors. The objective is to make a documented sourcing decision rather than automatically selecting internal development or outsourcing. A stakeholder register identifies stakeholders, a quality audit examines process effectiveness, and lessons learned provide knowledge from previous project experiences. Make-or-buy analysis is therefore the appropriate technique when the project team must compare internal production with external procurement.
Question 204. Which contract type generally places the greatest cost risk on the buyer when the final amount is uncertain?
- Fixed-price
- Cost-reimbursable
- Firm-fixed-price
- Fixed-price incentive
Correct Answer: 2. Cost-reimbursable.
Explanation:
A cost-reimbursable contract generally places more cost risk on the buyer because the buyer agrees to reimburse allowable costs incurred by the seller, often with an additional fee or incentive. The final amount may therefore vary depending on actual project costs. Fixed-price arrangements generally provide greater cost predictability for the buyer because the agreed price establishes a defined financial commitment, although specific contract terms can introduce other risks. The appropriate contract type depends on factors such as scope certainty, market conditions, supplier capabilities, and the distribution of risk. Understanding contract risk allocation helps project managers select and administer procurement arrangements appropriately.
Question 205. A project manager wants to identify all major deliverables and progressively break them into smaller manageable components. Which technique should be used?
- Decomposition
- Benchmarking
- Escalation
- Brainstorming
Correct Answer: 1. Decomposition.
Explanation:
Decomposition is the process of breaking project scope or deliverables into progressively smaller components until the work can be planned, estimated, assigned, and controlled effectively. It is a fundamental technique used when developing the work breakdown structure. For example, a major project deliverable can be divided into subdeliverables, work packages, and ultimately activities or tasks that the team can manage. Brainstorming may help generate ideas, while benchmarking compares performance or practices against other organizations or standards. Escalation transfers an issue or decision to a higher authority. Decomposition specifically addresses the need to organize complex project work into manageable and understandable components.
Question 206. Which document formally describes what a project is expected to produce and the boundaries of the work?
- Project scope statement
- Risk register
- Communications log
- Resource calendar
Correct Answer: 1. Project scope statement.
Explanation:
The project scope statement describes the project’s boundaries and provides a detailed understanding of what the project will and will not deliver. It commonly includes the project scope, major deliverables, assumptions, constraints, exclusions, and other information needed to establish a common understanding of the work. Clearly documenting scope helps prevent misunderstandings and reduces the likelihood of uncontrolled scope expansion. A risk register focuses on uncertain events, a communications log records communications, and a resource calendar identifies resource availability. The scope statement is therefore an important reference for planning, stakeholder communication, change evaluation, and determining whether proposed work belongs within the approved project.
Question 207. A project has a task that can begin three days before its predecessor is completely finished. What scheduling concept does this represent?
- Lag
- Lead
- Float
- Reserve
Correct Answer: 2. Lead.
Explanation:
A lead allows a successor activity to begin before its predecessor has completely finished. In the scenario, allowing the next task to begin three days before the previous task ends creates a scheduling overlap and represents lead time. A lag is the opposite concept because it introduces a waiting period between related activities. Float represents the amount of time an activity can be delayed without affecting a specified schedule objective, while reserve refers to time or cost set aside to address uncertainty. Understanding leads and lags helps project managers create realistic dependencies and optimize schedules without incorrectly treating overlapping work as an independent activity.
Question 208. What is the primary purpose of a schedule reserve?
- To replace the project baseline
- To provide additional time for known schedule uncertainty or risks
- To increase the project team’s salaries
- To eliminate all project dependencies
Correct Answer: 2. To provide additional time for known schedule uncertainty or risks.
Explanation:
A schedule reserve provides additional time within the overall planning approach to accommodate uncertainty, anticipated variability, or identified risks that could affect completion. It should be managed deliberately rather than treated as unlimited free time. The project manager should understand why the reserve exists, what conditions may justify using it, and how its use affects the overall schedule. A reserve does not replace the schedule baseline, eliminate dependencies, or represent compensation for team members. Proper use of schedule reserves can improve planning realism while maintaining transparency about uncertainty. Project teams should still monitor actual performance and address emerging issues rather than relying on reserve time as a substitute for control.
Question 209. Which type of requirement describes what the system or product must do?
- Functional requirement
- Organizational constraint
- Resource requirement
- Procurement requirement
Correct Answer: 1. Functional requirement.
Explanation:
A functional requirement describes a behavior, capability, or operation that a product, service, or system must provide. For example, an application might be required to allow users to reset their passwords, generate a report, or submit an online request. Functional requirements help the project team understand what the solution must accomplish. Nonfunctional requirements, by comparison, commonly describe characteristics such as performance, security, availability, usability, or reliability. Clearly identifying functional requirements helps stakeholders and project teams establish acceptance criteria and validate deliverables. It also provides a foundation for requirements traceability, testing, and change evaluation throughout the project lifecycle.
Question 210. Which requirement would be considered nonfunctional?
- Users can create new accounts
- The system generates monthly invoices
- The application must respond to requests within two seconds
- Customers can cancel an order
Correct Answer: 3. The application must respond to requests within two seconds.
Explanation:
A requirement specifying that an application must respond within two seconds is a nonfunctional requirement because it defines a performance characteristic rather than a specific business function. Functional requirements describe what the system does, such as creating accounts, generating invoices, or canceling orders. Nonfunctional requirements describe how well the system should perform or what qualities it must possess, including performance, security, reliability, availability, scalability, and usability. Nonfunctional requirements are important because a system may provide all required functions while still failing stakeholder expectations if it performs too slowly or does not meet required quality characteristics.
Question 211. What is the primary purpose of acceptance criteria?
- To define conditions that must be satisfied for a deliverable to be accepted
- To assign employees to departments
- To calculate the project’s total budget
- To identify every possible project risk
Correct Answer: 1. To define conditions that must be satisfied for a deliverable to be accepted.
Explanation:
Acceptance criteria define the specific conditions that a deliverable must satisfy before the customer, sponsor, or authorized stakeholder can formally accept it. They provide measurable or observable expectations that can be used during validation and acceptance activities. Clear acceptance criteria reduce ambiguity because the project team and stakeholders have a shared understanding of what constitutes an acceptable result. They are not intended to replace the budget, risk register, or organizational structure. Establishing acceptance criteria early can also help the team design, test, and verify deliverables against agreed requirements rather than relying on subjective judgments after the work is completed.
Question 212. A project team identifies a risk that could occur because a supplier may experience a shipping delay. What should be documented as a possible early warning sign?
- Risk trigger
- Project charter
- Scope baseline
- Acceptance criteria
Correct Answer: 1. Risk trigger.
Explanation:
A risk trigger is an event, condition, or warning sign that indicates a risk may be occurring or becoming more likely. For a supplier shipping-delay risk, examples could include repeated missed shipment confirmations, a notification from the supplier about transportation problems, or failure to meet an agreed preparation date. Monitoring triggers helps the project team recognize changing conditions early enough to implement the planned response. A project charter authorizes and establishes the project at a high level, while a scope baseline defines approved scope. Acceptance criteria specify conditions for deliverable acceptance. Risk triggers therefore support proactive risk monitoring and response management.
Question 213. A previously identified risk occurs and begins affecting project performance. How should the project team generally classify the event?
- Assumption
- Issue
- Constraint
- Milestone
Correct Answer: 2. Issue.
Explanation:
When a previously identified risk actually occurs and begins affecting the project, it becomes an issue that requires active management. The team should implement the appropriate risk response if one was planned, document the situation, assess its impact, and track actions until the issue is resolved or otherwise controlled. An assumption is something believed to be true for planning purposes, while a constraint limits the project and a milestone represents a significant point in the schedule. Converting an realized risk into an issue is an important distinction because risk management focuses on uncertainty, whereas issue management addresses a condition that is already happening.
Question 214. Which risk response strategy involves reducing the probability or impact of a threat?
- Accept
- Transfer
- Mitigate
- Escalate
Correct Answer: 3. Mitigate.
Explanation:
Mitigation involves taking action to reduce the probability that a threat will occur, reduce its potential impact, or both. For example, a project team concerned about data loss might implement additional backups, testing, monitoring, or security controls before a problem occurs. Acceptance means acknowledging the risk without taking proactive action beyond monitoring or preparing a contingency, while transfer shifts responsibility for some consequences to another party. Escalation is used when the risk is outside the project’s authority or scope and should be managed at a higher organizational level. Selecting mitigation requires understanding the source of the risk and identifying practical preventive actions.
Question 215. What is a residual risk?
- A risk that has been completely eliminated
- A risk remaining after a response has been implemented
- A risk that has never been identified
- A risk caused only by a project sponsor
Correct Answer: 2. A risk remaining after a response has been implemented.
Explanation:
Residual risk is the amount of risk that remains after the project team has implemented a risk response. Risk responses can reduce probability or impact but may not eliminate uncertainty completely. For example, adding security controls may substantially reduce the likelihood of a data breach, but some exposure can still remain. The remaining exposure should be assessed and monitored to determine whether additional action is necessary. A risk that is completely eliminated would no longer represent the same exposure. Recognizing residual risk is important because project teams should not assume that implementing one response automatically removes all uncertainty associated with the original threat.
Question 216. What is a secondary risk?
- A new risk created as a direct result of implementing a risk response
- A risk that has already been closed
- A risk with zero probability
- A risk documented only during project closure
Correct Answer: 1. A new risk created as a direct result of implementing a risk response.
Explanation:
A secondary risk is a new risk that arises because a response to another risk has been implemented. For example, a project may outsource a high-risk technical activity to reduce internal delivery risk, but outsourcing could introduce a new supplier-dependency or confidentiality risk. The new exposure should be identified, assessed, documented, and monitored just like other project risks. This demonstrates why risk management is an ongoing process rather than a one-time exercise. The team should consider not only whether a response reduces the original risk but also whether the chosen response introduces additional uncertainty that requires its own management strategy.
Question 217. Which activity is most appropriate when evaluating potential suppliers before awarding a procurement contract?
- Bid evaluation
- Project closure
- Requirements deletion
- Schedule compression
Correct Answer: 1. Bid evaluation.
Explanation:
Bid evaluation is used to assess supplier proposals against established selection criteria. Depending on the procurement, criteria may include technical capability, price, delivery schedule, experience, quality, security requirements, contractual terms, and ability to meet project specifications. A structured evaluation helps ensure that procurement decisions are based on documented requirements rather than informal preferences. Schedule compression focuses on reducing project duration, while project closure occurs after the project work has been completed. Requirements should not be deleted merely because proposals are being evaluated. Establishing clear evaluation criteria before reviewing bids also supports consistency and transparency in the supplier selection process.
Question 218. A project manager discovers that a critical supplier contract requires a service level that the supplier is not meeting. What should the project manager review first?
- Contract and SLA requirements
- Team vacation preferences
- Project lessons learned only
- The project charter’s original business justification
Correct Answer: 1. Contract and SLA requirements.
Explanation:
When a supplier is failing to meet a contractual service level, the project manager should first review the applicable contract terms and service-level agreement requirements. These documents establish what the supplier agreed to provide, expected performance levels, measurement criteria, remedies, reporting requirements, and escalation procedures. Reviewing the agreement provides an objective basis for determining whether performance is actually below the contractual requirement and what actions are available. Team vacation preferences and historical lessons learned do not establish the supplier’s current contractual obligations. The project charter may provide high-level project context, but detailed supplier performance expectations are normally found in procurement documentation and the contract.
Question 219. Which project management approach is most suitable when requirements are expected to evolve through frequent stakeholder feedback and short delivery cycles?
- Predictive
- Adaptive
- Sequential-only
- Fixed-scope-only
Correct Answer: 2. Adaptive.
Explanation:
An adaptive project management approach is designed for environments where requirements may change as stakeholders provide feedback and the team learns more about the solution. Work is commonly delivered in shorter cycles or iterations, allowing stakeholders to review results and influence subsequent work. This approach can be useful when the final solution is not completely understood at the beginning of the project. A predictive approach generally emphasizes detailed planning and a more stable scope before execution. The choice between approaches should consider the project’s uncertainty, organizational environment, stakeholder expectations, regulatory needs, and type of deliverable rather than assuming that one method applies to every project.
Question 220. Before formally closing a project, what should the project manager verify regarding the final deliverable?
- That the deliverable has received formal acceptance
- That all project risks have been completely eliminated
- That no project documentation remains
- That every stakeholder has become a project team member
Correct Answer: 1. That the deliverable has received formal acceptance.
Explanation:
Formal acceptance confirms that the authorized customer, sponsor, or stakeholder has reviewed the final deliverable and determined that it meets the agreed requirements and acceptance criteria. This confirmation is an important closure prerequisite because the project should not be considered complete merely because the project team believes the work is finished. The project manager should also complete remaining administrative activities such as final documentation, procurement closure, lessons learned, resource release, and archival. Not every risk must be completely eliminated, and project documentation should be retained rather than deleted. Formal acceptance provides evidence that the project’s primary deliverables have satisfied the agreed expectations.