View Full PMI PMI-RMP Exam Dumps and Practice Test Dumps
Question: 141. During risk identification, the project team discovers that several risks are based on assumptions that have not yet been validated. What should the risk management professional do FIRST?
- Remove all risks based on assumptions from the risk register
2. Validate the assumptions and assess how they affect identified risks
3. Escalate every assumption-related risk to the sponsor
4. Assign contingency reserves to all assumption-related risks
Correct Answer: 2
Explanation:
Unvalidated assumptions can create uncertainty and may influence the probability or impact of identified risks. The risk management professional should first validate the assumptions and determine whether they remain reasonable. This assessment helps establish whether the associated risks are still relevant and whether their probability, impact, or response strategies need adjustment. Removing the risks prematurely could cause important uncertainties to be overlooked, while escalating every assumption-related risk would be disproportionate. Contingency reserves should be considered only after the relevant risks and potential responses have been properly assessed.
Question: 142. A project team wants to determine which individual risks contribute most significantly to variability in the project’s total cost estimate. Which quantitative technique is MOST appropriate?
- Sensitivity analysis
2. Risk categorization
3. Delphi technique
4. Probability-impact matrix
Correct Answer: 1
Explanation:
Sensitivity analysis helps determine which individual risks or uncertain variables have the greatest influence on a project objective, such as total cost. By identifying the variables that contribute most to cost variability, the team can focus attention and response planning on the most influential sources of uncertainty. A probability-impact matrix is primarily a qualitative prioritization technique, while Delphi is used to obtain structured expert input. Risk categorization organizes risks into groups but does not quantify their contribution to overall cost variability.
Question: 143. A project manager identifies an opportunity that could significantly reduce the project’s completion time if successfully realized. The organization has the authority and resources to make the opportunity occur. Which response strategy should be considered?
- Share
2. Enhance
3. Exploit
4. Accept
Correct Answer: 3
Explanation:
Exploitation is an opportunity response strategy used when the project team takes action to ensure that an opportunity occurs. In this situation, the organization has both the authority and resources necessary to directly pursue the opportunity, making exploit an appropriate response to evaluate. Enhancement would increase the probability or impact of an opportunity but would not necessarily guarantee that it occurs. Sharing involves allocating ownership to a third party better positioned to capture the opportunity, while acceptance means taking advantage of it if it occurs without proactive action to ensure realization.
Question: 144. A previously identified risk has become more urgent because its trigger condition is expected to occur within the next few days. What should the risk management professional do?
- Reassess the risk and prioritize the appropriate response
2. Close the risk because the trigger is approaching
3. Wait until the trigger actually occurs before taking action
4. Remove the risk from the risk register and document it as an issue
Correct Answer: 1
Explanation:
Risk urgency reflects how soon a risk may require a response. When a trigger condition is approaching, the risk management professional should reassess its probability, impact, timing, and response readiness. The team may need to implement a planned response or prepare contingency actions before the event occurs. Waiting until the risk becomes an issue can reduce available response options. The risk should not automatically be closed simply because its trigger is approaching. Instead, the approaching trigger provides important information for monitoring and response execution.
Question: 145. During quantitative risk analysis, the project team runs thousands of simulations using probability distributions for cost estimates and risk events. What technique is being used?
- Decision tree analysis
2. Monte Carlo simulation
3. Expert judgment
4. Root cause analysis
Correct Answer: 2
Explanation:
Monte Carlo simulation uses repeated random sampling from probability distributions to model possible outcomes of uncertain project variables. In project risk management, it can be used to estimate ranges and probabilities for objectives such as cost or schedule completion. Running thousands of simulations allows the team to observe the distribution of possible outcomes rather than relying on a single deterministic estimate. Decision tree analysis compares alternatives and possible outcomes, expert judgment relies on informed expertise, and root cause analysis investigates underlying causes of risks.
Question: 146. A project risk owner reports that a planned mitigation has reduced the probability of a threat, but the remaining impact is still significant. What should the team do NEXT?
- Close the risk because its probability decreased
2. Ignore the remaining impact because mitigation was implemented
3. Reassess the residual risk and determine whether additional action is needed
4. Remove the risk owner from the risk register
Correct Answer: 3
Explanation:
A risk does not necessarily disappear when a response reduces its probability. The remaining exposure is known as residual risk and should be reassessed after the response is implemented. If the residual impact remains significant, the team may need additional mitigation, contingency planning, escalation, or another appropriate response. Closing the risk simply because probability decreased could leave meaningful exposure unmanaged. Effective risk monitoring therefore considers the risk’s current probability, impact, exposure, triggers, and response effectiveness.
Question: 147. A project team groups identified risks according to technical, external, organizational, and project-management sources. What is the PRIMARY purpose of this approach?
- Increase the project’s contingency reserve automatically
2. Eliminate low-probability risks
3. Facilitate structured analysis and identify common areas of risk exposure
4. Convert qualitative risks into quantitative values
Correct Answer: 3
Explanation:
Risk categorization organizes risks into meaningful groups based on common characteristics or sources. Categories can help the team identify concentration areas, recurring causes, ownership patterns, and gaps in risk identification. For example, a large number of technical risks may indicate an area requiring additional expertise or focused response planning. Categorization does not automatically increase contingency reserves, eliminate risks, or convert qualitative information into quantitative values. Its primary value is improving the structure and usefulness of risk analysis and communication.
Question: 148. A project sponsor states that the organization is willing to accept moderate cost uncertainty but has very little tolerance for missing a regulatory deadline. What does this statement primarily describe?
- Risk appetite and risk attitude toward different objectives
2. A risk breakdown structure
3. A risk trigger
4. A secondary risk
Correct Answer: 1
Explanation:
Organizations and stakeholders may have different attitudes toward uncertainty depending on the project objective. In this scenario, the sponsor is relatively comfortable with moderate cost uncertainty but has very low tolerance for regulatory schedule deviation. This illustrates risk appetite and stakeholder risk attitudes across different objectives. Understanding these attitudes helps the project team establish appropriate priorities, thresholds, and response strategies. A risk trigger is a warning condition, a risk breakdown structure categorizes sources, and a secondary risk arises as a consequence of implementing a response.
Question: 149. A risk response requires additional funds that were not included in the original activity estimate. Which project management resource should be reviewed to determine whether the response can be funded without changing the overall project budget baseline?
- Management reserve
2. Lessons learned repository
3. Risk breakdown structure
4. Stakeholder register
Correct Answer: 1
Explanation:
Management reserve is a portion of the project budget or schedule intended for unforeseen work within the scope of the project, subject to organizational governance. When an unplanned risk response requires funding, the project team may need to review available reserves and follow the organization’s change and approval procedures. The risk register and response plan still need to be updated accordingly. A lessons learned repository, risk breakdown structure, or stakeholder register does not provide funding for unexpected response activities.
Question: 150. A risk analyst wants to understand how reliable the probability and impact estimates are before performing quantitative analysis. Which factor should receive particular attention?
- Number of project milestones
2. Quality of risk data
3. Number of stakeholders
4. Size of the project team
Correct Answer: 2
Explanation:
The quality of risk data directly affects the reliability of risk analysis. Probability and impact estimates based on incomplete, outdated, biased, or poorly understood information may produce misleading results. Before relying on quantitative outputs, the risk analyst should evaluate whether the underlying data is sufficiently accurate, relevant, timely, and complete for the intended analysis. The number of milestones, stakeholders, or team members may influence project complexity but does not by itself determine whether risk estimates are reliable.
Question: 151. A threat is outside the project manager’s authority and could affect several projects across the organization. What is the MOST appropriate response?
- Escalate the risk to the appropriate organizational authority
2. Accept the risk without documenting it
3. Transfer the risk to an individual team member
4. Remove the risk because it is outside the project scope
Correct Answer: 1
Explanation:
A risk should be escalated when it falls outside the project’s authority or boundaries and requires action by a higher-level entity. A threat affecting several projects may require portfolio, program, organizational, legal, or executive-level management. The project team should document the risk and communicate it through the appropriate governance structure. Simply accepting or removing the risk would not address the organizational exposure. Transferring it to an individual team member also would not resolve the authority issue.
Question: 152. After implementing a risk response, the team discovers that the response itself has created an unexpected new technical risk. How should this new risk be classified?
- Residual risk
2. Secondary risk
3. Overall project risk
4. Accepted risk
Correct Answer: 2
Explanation:
A secondary risk is a new risk that arises as a direct result of implementing a risk response. For example, changing a technical design to mitigate one threat might introduce compatibility or integration problems. The new risk should be documented, analyzed, assigned to an appropriate owner, and addressed through a suitable response if necessary. Residual risk refers to the exposure that remains after a response is implemented. Overall project risk represents the effect of uncertainty on the project as a whole rather than a specific new risk caused by a response.
Question: 153. A team is evaluating whether to pursue a risky technology opportunity. The opportunity has a 40% probability of generating a $50,000 benefit and a 60% probability of generating no additional benefit. What is the opportunity’s expected monetary value?
- $10,000
2. $20,000
3. $30,000
4. $50,000
Correct Answer: 2
Explanation:
Expected monetary value is calculated by multiplying each possible outcome by its probability and then summing the results. In this case, the expected benefit is calculated as 0.40 × $50,000, which equals $20,000. The zero-benefit outcome contributes nothing to the total expected value. Therefore, the opportunity’s EMV is $20,000. EMV is useful when comparing uncertain alternatives or evaluating the expected financial effect of risks and opportunities, although the decision should also consider other relevant project factors.
Question: 154. A project team has identified several risks but has not yet determined which ones require detailed quantitative analysis. What should the team generally do first?
- Perform qualitative risk analysis to prioritize the risks
2. Build a Monte Carlo model for every identified risk
3. Assign contingency reserves to every risk
4. Close all low-probability risks immediately
Correct Answer: 1
Explanation:
Qualitative risk analysis is generally used to assess and prioritize identified risks based on characteristics such as probability, impact, urgency, and other relevant factors. The results can help the team determine which risks warrant more detailed quantitative analysis. Performing complex quantitative modeling for every identified risk may consume significant resources without providing proportional value. Likewise, low-probability risks should not automatically be closed without considering their potential impact and other characteristics. Prioritization provides a structured basis for deciding where deeper analysis is appropriate.
Question: 155. A project manager notices that a risk’s probability and impact ratings have changed substantially since the previous risk review because project conditions have evolved. What should happen?
- Keep the original ratings to preserve historical consistency
2. Delete the original risk assessment
3. Reassess and update the risk information based on current conditions
4. Wait until the risk occurs before updating its rating
Correct Answer: 3
Explanation:
Risk assessments should reflect current project conditions. When circumstances change significantly, the team should reassess probability, impact, urgency, response effectiveness, and other relevant information. Maintaining outdated ratings simply for historical consistency can result in poor decision-making. The historical assessment can remain available as part of the project’s records, but the active risk information should be updated. Waiting until the risk occurs would prevent the team from using current information to manage the uncertainty proactively.
Question: 156. A risk owner is responsible for monitoring a trigger and initiating the agreed response when the trigger condition occurs. What is the key benefit of assigning this responsibility explicitly?
- It guarantees that the risk will never occur
2. It establishes accountability for monitoring and response execution
3. It eliminates the need for risk reviews
4. It transfers overall project risk to the risk owner
Correct Answer: 2
Explanation:
Explicitly assigning a risk owner establishes accountability for monitoring the risk and taking or coordinating the agreed response when appropriate. This helps ensure that warning signs are not overlooked and that response actions are initiated in a timely manner. Assigning ownership does not guarantee that the risk will not occur, eliminate the need for ongoing reviews, or transfer overall project risk to an individual. The project manager and governance structure may retain broader accountability while the risk owner manages the assigned risk.
Question: 157. A quantitative risk analysis shows that there is only a 55% probability of completing the project by the