Question: 101. Which PRINCE2 7 principle emphasizes making decisions based on lessons from previous and current projects?

  1. Manage by exception
    2. Learn from experience
    3. Focus on products
    4. Manage by stages

Correct Answer: 2. Learn from experience

Explanation:

The Learn from Experience principle requires projects to actively seek, record, and apply relevant lessons. Lessons can come from previous projects, earlier stages of the current project, or experiences occurring during ongoing work. The objective is not simply to document lessons at closure but to use them to improve decisions and project performance throughout the project. Lessons can influence planning, risk management, communication, quality, delivery approaches, and other management arrangements. Applying experience helps the project avoid repeating known problems and encourages the reuse of effective practices. The principle therefore makes learning an ongoing activity rather than a final administrative exercise.

Question: 102. Which role is accountable for ensuring that the project remains focused on achieving its intended benefits and business justification?

  1. Project Support
    2. Team Manager
    3. Senior Supplier
    4. Project Executive

Correct Answer: 4. Project Executive

Explanation:

The Project Executive has overall accountability for ensuring that the project remains aligned with the organization’s investment and business objectives. The Executive represents the business perspective and ensures that the Business Case remains sufficiently justified as circumstances change. This includes considering whether expected benefits, costs, risks, and strategic objectives continue to support the project’s viability. The Senior User focuses on user needs and benefits from the user perspective, while the Senior Supplier represents technical and supplier interests. The Project Manager manages the project within delegated authority. The Executive therefore holds the ultimate accountability for maintaining the business justification.

Question: 103. What is the main purpose of product-based planning?

  1. To identify the products that must be created and the work required to deliver them
    2. To replace all project controls with team-level decisions
    3. To record only the project’s financial expenditure
    4. To determine which stakeholders should receive reports

Correct Answer: 1. To identify the products that must be created and the work required to deliver them

Explanation:

Product-based planning starts by identifying the products required by the project and then determining the activities and resources needed to create those products. It helps the project focus on outputs rather than simply listing activities. This approach can clarify dependencies, quality expectations, acceptance criteria, and the sequence of product creation. By understanding what must be delivered, the project team can develop more meaningful plans and estimates. Financial tracking, stakeholder communication, and project controls remain important but are not the primary purpose of product-based planning. The approach directly supports the Focus on Products principle.

Question: 104. Which management product provides a description of a specific product, including its purpose, composition and quality criteria?

  1. Risk Register
    2. Highlight Report
    3. Product Description
    4. Communication Management Approach

Correct Answer: 3. Product Description

Explanation:

A Product Description defines the characteristics of a particular product. It can explain the product’s purpose, composition, derivation, quality expectations, quality criteria, quality methods, and acceptance-related information as appropriate. Product Descriptions help ensure that everyone involved understands what is required and how the product’s quality will be assessed. The Risk Register records risk information, the Highlight Report communicates project progress to the Project Board, and the Communication Management Approach defines communication arrangements. Clear Product Descriptions support product-based planning and quality management by providing an agreed basis for creating and verifying individual products.

Question: 105. What is the main purpose of a Quality Register?

  1. To record project expenditure
    2. To record planned and completed quality-related activities
    3. To authorize the next management stage
    4. To document stakeholder complaints only

Correct Answer: 2. To record planned and completed quality-related activities

Explanation:

The Quality Register provides a record of planned and completed quality-related activities. It can be used to track activities such as quality reviews, tests, inspections, or other agreed quality methods, together with relevant information about their status and results. This provides visibility into whether planned quality activities are being carried out and helps support quality control. It is different from a Product Description, which defines the quality requirements for an individual product. The Quality Register also differs from the Risk Register and Issue Register, which focus on uncertainty and issues respectively. Maintaining quality records helps provide evidence that required quality activities have taken place.

Question: 106. Which PRINCE2 7 process is primarily concerned with accepting, executing and delivering Work Packages?

  1. Managing a Stage Boundary
    2. Closing a Project
    3. Managing Product Delivery
    4. Directing a Project

Correct Answer: 3. Managing Product Delivery

Explanation:

Managing Product Delivery coordinates the relationship between the Project Manager and those responsible for creating specialist products. It includes accepting Work Packages, executing the authorized work, reporting progress, and delivering completed products back to the Project Manager. This process helps ensure that product delivery occurs within the agreed requirements and controls. Directing a Project is concerned with Project Board decisions and overall direction, while Managing a Stage Boundary focuses on preparing information for the next-stage decision. Closing a Project focuses on controlled completion. Managing Product Delivery therefore provides the main process for coordinating product creation.

Question: 107. What should happen when a forecast indicates that a project-level tolerance will be exceeded?

  1. The Project Manager should continue without escalation
    2. The relevant exception should be escalated to the appropriate higher authority
    3. The affected tolerance should be removed
    4. The project should automatically be closed

Correct Answer: 2. The relevant exception should be escalated to the appropriate higher authority

Explanation:

A forecast that a project-level tolerance will be exceeded indicates that the matter is outside the authority delegated to the current management level. It should therefore be escalated to the appropriate higher authority, normally the Project Board or another authority defined by the project’s governance arrangements. The escalation should provide sufficient information to allow an informed decision about the available options and appropriate response. The Project Manager should not simply continue without authorization or change the tolerance independently. Exceeding a tolerance also does not automatically mean that the project must be terminated; the appropriate authority determines the response.

Question: 108. Which report is most closely associated with regular reporting from a delivery team to the Project Manager?

  1. Checkpoint Report
    2. End Project Report
    3. Highlight Report
    4. Exception Report

Correct Answer: 1. Checkpoint Report

Explanation:

A Checkpoint Report provides regular information from a Team Manager or delivery responsibility to the Project Manager about the progress of a Work Package. It can include information about work completed, work remaining, issues, risks, and forecasts. This allows the Project Manager to monitor delivery while avoiding unnecessary day-to-day intervention in specialist work. A Highlight Report is normally provided by the Project Manager to the Project Board, while an Exception Report communicates a forecast exception requiring escalation. An End Project Report is prepared at project closure. The Checkpoint Report therefore provides the appropriate communication channel for regular delivery-level progress reporting.

Question: 109. Which statement best describes an issue in PRINCE2 7?

  1. An issue is always a threat to the project’s objectives
    2. An issue is only a problem discovered after project closure
    3. An issue is a matter that requires assessment and management because it may affect the project
    4. An issue is identical to an uncertain future event

Correct Answer: 3. An issue is a matter that requires assessment and management because it may affect the project

Explanation:

An issue is a matter that requires consideration and management because it may affect the project, its products, or its objectives. PRINCE2 issue management includes different types of issues, such as requests for change, off-specifications, and problems or concerns that require assessment. An issue is not necessarily a threat; it may represent a requested change or another matter requiring a decision. A risk is different because it concerns uncertainty about a possible future event or set of events. Proper issue management ensures that matters are assessed and controlled rather than being allowed to affect the project without appropriate consideration.

Question: 110. Which document provides the detailed plan for the work that will be carried out during a particular stage?

  1. Project Brief
    2. Stage Plan
    3. Business Case
    4. Lessons Log

Correct Answer: 2. Stage Plan

Explanation:

The Stage Plan provides detailed information about how a particular management stage will be delivered and controlled. It can define the products to be created, activities, resources, schedules, tolerances, controls, and other information required for effective stage management. It translates the broader project direction into a practical plan for the current stage. The Project Brief provides an early project definition, the Business Case supports continued justification, and the Lessons Log captures lessons. Stage planning therefore provides the Project Manager and delivery teams with a clear basis for managing the work while staying within agreed project and stage controls.

Question: 111. Which role is normally responsible for directing the project at the governance level rather than managing it day to day?

  1. Project Board
    2. Project Support
    3. Team Manager
    4. Project Manager

Correct Answer: 1. Project Board

Explanation:

The Project Board provides governance and overall direction rather than managing the project’s daily activities. It represents the business, user, and supplier interests and makes key decisions within its authority. The Project Manager is responsible for day-to-day management and coordinates the work required to deliver the project’s products. Team Managers may manage specialist delivery work, while Project Support provides administrative and specialist support. Keeping governance separate from daily management allows the Project Board to focus on strategic decisions, continued justification, authorization, and exception handling without becoming involved in routine delivery activities.

Question: 112. Which practice is responsible for ensuring that the project remains justified throughout its life?

  1. Quality
    2. Risk
    3. Issues
    4. Business Case

Correct Answer: 4. Business Case

Explanation:

The Business Case practice ensures that the project continues to have a valid justification throughout its life. The justification should be reviewed as circumstances change and at appropriate governance points. Factors such as expected benefits, costs, risks, strategic alignment, and the project’s changing environment can affect whether the investment remains worthwhile. The Quality practice focuses on achieving required product quality, Risk addresses uncertainty, and Issues manages matters requiring assessment and control. Continued business justification is important because a project that was worthwhile when started may no longer provide sufficient value if its circumstances or assumptions change.

Question: 113. What is the purpose of an Exception Plan?

  1. To provide a replacement plan for a stage or project when an exception requires revised direction
    2. To record every lesson from previous projects
    3. To describe the quality criteria of a single product
    4. To replace the Risk Register

Correct Answer: 1. To provide a replacement plan for a stage or project when an exception requires revised direction

Explanation:

An Exception Plan is developed when an exception has been identified and an alternative plan is required to bring the project or stage back under control. It provides a revised plan based on the decision made by the appropriate authority following the exception. The Exception Plan can replace the affected Stage Plan or, where appropriate, the Project Plan. It is not a general lessons record, Product Description, or risk record. Exception planning supports Manage by Exception by providing a structured way to respond when agreed tolerances are forecast to be exceeded and a new approved direction is required.

Question: 114. Which activity is most closely associated with the Closing a Project process?

  1. Authorizing the first project stage
    2. Preparing the Project Brief
    3. Confirming product acceptance and evaluating project performance
    4. Creating the initial outline Business Case

Correct Answer: 3. Confirming product acceptance and evaluating project performance

Explanation:

Closing a Project provides a controlled way to complete the project. Activities can include confirming that the project’s products have been accepted, assessing project performance, ensuring that outstanding actions and follow-on recommendations are addressed, and preparing appropriate closure information. The process also supports the transition from project delivery to the operational or business environment. Authorizing the first stage belongs to project direction, while preparing the Project Brief and outline Business Case occurs during Starting up a Project. Controlled closure helps ensure that the project ends in an orderly manner and that useful information and lessons are retained.

Question: 115. Which statement best describes the relationship between a risk and an issue?

  1. A risk is an uncertain event, while an issue is a matter that has occurred or requires management
    2. Risks and issues are always recorded in the same document
    3. An issue can never result from a risk occurring
    4. A risk is always a negative event and an issue is always positive

Correct Answer: 1. A risk is an uncertain event, while an issue is a matter that has occurred or requires management

Explanation:

A risk relates to uncertainty: an event or set of events that may occur and affect project objectives. An issue is a matter that has arisen and requires consideration or management. If a previously identified risk occurs, it may become an issue because the uncertainty has materialized and now requires action. Risks can represent threats or opportunities, so they are not always negative. Risks and issues may have related information but are managed through their respective practices and controls. Understanding the distinction helps the project respond appropriately to uncertainty while ensuring that actual matters are not left unmanaged.

Question: 116. Which principle encourages project management to define the desired outputs before determining the activities needed to create them?

  1. Manage by exception
    2. Focus on products
    3. Learn from experience
    4. Manage by stages

Correct Answer: 2. Focus on products

Explanation:

Focus on Products emphasizes understanding and defining the required outputs before deciding how the work will be performed. Clear product definitions help identify what needs to be created, the quality criteria that must be satisfied, how products will be accepted, and the work needed to produce them. This approach supports product-based planning and helps prevent teams from becoming focused only on activities without understanding the intended outputs. Manage by exception focuses on delegated authority and tolerances, Learn from Experience focuses on lessons, and Manage by Stages focuses on governance through management stages. Product focus therefore provides a clear foundation for planning and delivery.

Question: 117. What is the primary purpose of the Project Product Description?

  1. To define how the final project product will be created and what characteristics it must have
    2. To record individual project risks
    3. To authorize individual team members
    4. To report progress to the Project Board

Correct Answer: 1. To define how the final project product will be created and what characteristics it must have

Explanation:

The Project Product Description defines the project’s final product and establishes the characteristics and quality expectations that the final product must satisfy. It provides an important basis for understanding the project’s scope and for determining whether the final outcome can be accepted. It can include the purpose, composition, quality expectations, acceptance criteria, and other relevant characteristics. Individual risks belong in risk management records, progress reporting is handled through appropriate reports, and team authorization is managed through other project controls. Defining the final product clearly helps align planning, delivery, quality management, and stakeholder expectations.

Question: 118. Which statement about the People element in PRINCE2 7 is most accurate?

  1. It replaces all project management practices
    2. It focuses only on recruitment
    3. It recognizes the importance of leadership, collaboration, relationships and stakeholder engagement
    4. It applies only to the Project Manager

Correct Answer: 3. It recognizes the importance of leadership, collaboration, relationships and stakeholder engagement

Explanation:

The People element recognizes that successful project management depends on people, relationships, leadership, communication, and collaboration. PRINCE2 7 gives greater explicit attention to the human aspects of project work, including how people interact, how stakeholders are engaged, and how leadership supports effective delivery. It does not replace the PRINCE2 practices or apply only to the Project Manager. Recruitment can be relevant but is only one possible aspect of people management. Considering the people involved helps the project understand expectations, manage relationships, support effective teamwork, and respond appropriately to organizational and stakeholder dynamics.

Question: 119. What should be considered when defining how sustainability will be managed within a PRINCE2 7 project?

  1. Only the project’s advertising requirements
    2. Relevant sustainability objectives, impacts and performance considerations
    3. Only the Project Manager’s personal preferences
    4. Only the number of products to be delivered

Correct Answer: 2. Relevant sustainability objectives, impacts and performance considerations

Explanation:

PRINCE2 7 recognizes sustainability as a relevant consideration that can be incorporated into project management and performance. Depending on the project’s context, this can involve considering sustainability objectives, environmental or social impacts, relevant requirements, and how sustainability performance will be monitored. The exact approach should be tailored to the project and its organizational environment. Sustainability should not be reduced to a single measure such as the number of products delivered, nor should it depend solely on individual preference. Considering sustainability as part of project management can help ensure that important impacts and objectives are identified and addressed appropriately.

Question: 120. Which statement best explains why PRINCE2 7 uses management stages?

  1. To prevent the Project Board from making decisions
    2. To divide the project into manageable sections with decision points for continued control
    3. To ensure every project has the same number of stages
    4. To eliminate the need for project planning

Correct Answer: 2. To divide the project into manageable sections with decision points for continued control

Explanation:

Managing by stages divides the project into manageable sections and provides defined points at which progress, continued justification, plans, risks, issues, and other information can be reviewed. These decision points allow the Project Board to authorize the next stage based on current information rather than committing the entire project without review. The number and structure of stages should be appropriate to the project’s circumstances and can therefore be tailored. Stages do not eliminate planning; instead, they support progressive planning and control. This approach helps governance remain informed while allowing the Project Manager appropriate authority during each management stage.