View Full Scrum PSM I Exam Dumps and Practice Test Dumps.
Question 61
Who decides whether a Product Backlog item provides enough value?
- Product Owner
- Scrum Master
- Developers
- Release coordinator
Correct Answer: 1
Explanation:
The Product Owner is accountable for maximizing the value of the product resulting from the Scrum Team’s work. This means the Product Owner considers product value when managing and ordering Product Backlog items. Developers contribute technical information, estimates, and implementation considerations, while the Scrum Master supports effective Scrum usage. Other organizational roles may provide useful input, but they do not replace the Product Owner’s accountability. Product value is influenced by many factors, including customer needs, business conditions, risks, and learning. The Product Owner uses available evidence to make appropriate ordering and product decisions.
Question 62
What should Developers do with newly discovered Sprint work?
- Reject every new discovery
- Update the Sprint Backlog
- Transfer responsibility to stakeholders
- Wait until the next release
Correct Answer: 2
Explanation:
The Sprint Backlog is a living plan that evolves during the Sprint. As Developers learn more about the work, they may add, remove, or adjust work needed to achieve the Sprint Goal. Newly discovered work does not automatically have to wait for another Sprint or release. Developers remain responsible for adapting their plan. The Product Owner can collaborate with Developers when scope clarification is useful, particularly when changes affect the Sprint Goal. This flexibility allows the team to respond to reality while maintaining the objective that gives the Sprint its purpose.
Question 63
Which event provides the formal opportunity to discuss improvements?
- Product Backlog refinement
- Sprint Review
- Sprint Retrospective
- Daily coordination session
Correct Answer: 3
Explanation:
The Sprint Retrospective provides the dedicated opportunity for the Scrum Team to inspect how the Sprint went and identify ways to improve quality and effectiveness. The team considers people, interactions, processes, tools, and the Definition of Done. The Sprint Review instead focuses on inspecting the product outcome and discussing future adaptations. Product Backlog refinement can help clarify upcoming work but is not a formal Scrum event. The Daily Scrum focuses on progress toward the Sprint Goal. The Retrospective therefore has the specific purpose of improving the team’s way of working.
Question 64
Who determines the technical approach for completing Sprint work?
- Business sponsor
- Product Owner
- Scrum Master
- Developers
Correct Answer: 4
Explanation:
Developers determine how selected work will be accomplished. Their technical expertise enables them to choose appropriate approaches, create an actionable plan, and adapt that plan as circumstances change. The Product Owner communicates product direction and value but does not dictate implementation details. The Scrum Master supports the team’s effectiveness and understanding of Scrum rather than acting as a technical director. External business roles can provide useful context, but they do not own the technical implementation decision. This supports self-management and places technical decisions with the professionals performing the work.
Question 65
What does the Sprint Goal provide to Developers?
- A shared objective for the Sprint
- A fixed list of personal assignments
- A permanent product architecture
- A quarterly employee evaluation
Correct Answer: 1
Explanation:
The Sprint Goal provides a shared objective for the Sprint. It explains why the Sprint is valuable and gives Developers a common direction while allowing flexibility in the exact work required. The goal is not a list of individual assignments or a technical architecture. It also has nothing to do with employee performance evaluations. When circumstances change, Developers can adapt the Sprint Backlog while maintaining focus on the Sprint Goal. This combination of stable purpose and flexible implementation allows Scrum Teams to respond to emerging information without losing sight of the intended Sprint outcome.
Question 66
When should a Product Backlog be refined?
- Only after product launch
- Continuously as needed
- Exclusively during Sprint Planning
- Once before the first Sprint
Correct Answer: 2
Explanation:
Product Backlog refinement is an ongoing activity used to add detail, order, and clarity to Product Backlog items. It is not a formal Scrum event and does not occur only at one predetermined moment. The Scrum Team may refine items as necessary based on the context and upcoming work. Waiting until product launch or restricting refinement to Sprint Planning can make future work less understood and reduce preparation for upcoming decisions. Effective refinement helps create transparency and shared understanding while keeping the Product Backlog useful and adaptable as the product evolves.
Question 67
What does the Product Goal give the Scrum Team?
- A detailed coding procedure
- A long-term product target
- A daily meeting script
- A mandatory staffing chart
Correct Answer: 2
Explanation:
The Product Goal describes a future state of the product and provides a longer-term target for the Scrum Team. It gives context to Product Backlog management and helps connect individual Sprints to broader product development. The Product Goal is not a technical coding procedure, a meeting script, or an organizational staffing chart. The Scrum Team should fulfill or abandon one Product Goal before taking on the next. Having a clear Product Goal helps the Product Owner order work meaningfully and gives Developers context for understanding why particular product improvements are important.
Question 68
What happens when work cannot satisfy the Definition of Done?
- It becomes a completed Increment
- It receives automatic approval
- It remains unfinished
- It is released as experimental functionality
Correct Answer: 3
Explanation:
Work that does not satisfy the Definition of Done remains unfinished and cannot be considered part of the Increment. The Definition of Done establishes the quality standard required for completed work. Marking incomplete work as an Increment would reduce transparency and could cause stakeholders to misunderstand the actual product state. Depending on the situation, unfinished work may be returned to the Product Backlog for future consideration. The important point is that completion is determined by the Definition of Done, not by how much effort has been spent or whether someone informally considers the work nearly finished.
Question 69
Which Scrum value encourages concentration on essential work?
- Courage
- Respect
- Focus
- Openness
Correct Answer: 3
Explanation:
Focus is one of the five Scrum values. It encourages the Scrum Team to concentrate on the work of the Sprint and the goals of the Scrum Team. Focus helps reduce unnecessary distractions and supports progress toward valuable outcomes. Courage helps people address difficult matters, Respect recognizes people as capable individuals, and Openness encourages transparency. Commitment is another Scrum value that supports dedication to goals. These values work together rather than functioning independently. Focus is specifically associated with concentrating attention and effort on the objectives that matter most.
Question 70
Who can delegate Product Owner responsibilities while retaining accountability?
- Product Owner
- Scrum Master
- Developers collectively
- Stakeholder committee
Correct Answer: 1
Explanation:
The Product Owner may delegate activities related to Product Backlog management to others, but accountability remains with the Product Owner. Delegation can be useful when a Product Owner works with specialists or other members of the organization who can assist with specific tasks. However, delegation does not transfer the underlying accountability for maximizing product value and managing the Product Backlog effectively. The Scrum Master supports Scrum adoption, Developers create the Increment, and stakeholders provide valuable input. None of these accountabilities replaces the Product Owner’s responsibility for product value and backlog management.
Question 71
What should happen if a Sprint Goal becomes unnecessary?
- Developers continue indefinitely
- Product Owner may cancel the Sprint
- Scrum Master extends the timebox
- Stakeholders rewrite the Definition of Done
Correct Answer: 2
Explanation:
If the Sprint Goal becomes obsolete, the Product Owner may cancel the Sprint. The Sprint Goal provides the purpose of the Sprint, so when that purpose is no longer relevant, continuing the Sprint may no longer provide sufficient value. Cancellation does not mean the Sprint duration is extended or that the Definition of Done is rewritten. The Scrum Master can help everyone understand Scrum and facilitate the situation, but does not possess the authority to cancel the Sprint. Developers also do not independently cancel or extend the Sprint. The Product Owner holds this authority.
Question 72
What is inspected during the Daily Scrum?
- Annual organizational strategy
- Progress toward the Sprint Goal
- Customer contract terms
- Individual salary expectations
Correct Answer: 2
Explanation:
Developers use the Daily Scrum to inspect progress toward the Sprint Goal and determine whether the Sprint Backlog needs adaptation. It is a short event focused on the current Sprint rather than a broad organizational management meeting. Developers may discuss their coordination needs in different ways, provided the event supports inspection and adaptation. Annual strategy, compensation discussions, and contract negotiations are outside the Daily Scrum’s purpose. The event helps Developers maintain awareness of their progress and adjust their immediate plan when new information or obstacles emerge.
Question 73
What does the Sprint Review primarily support?
- Future product adaptation
- Individual attendance monitoring
- Department budget approval
- Technical certification testing
Correct Answer: 1
Explanation:
The Sprint Review supports inspection of the Sprint outcome and adaptation of the Product Backlog and future product direction. The Scrum Team and relevant stakeholders collaborate to understand what has been achieved and what has changed in the environment. This information can influence future priorities and product decisions. The event is not intended for attendance monitoring, department budget approval, or technical certification testing. Its value comes from examining the actual product result and using current evidence to determine what should happen next. This makes the Sprint Review an important empirical feedback point.
Question 74
Which artifact communicates the quality standard for completed work?
- Sprint Backlog
- Product Goal
- Definition of Done
- Product Increment
Correct Answer: 3
Explanation:
The Definition of Done communicates the formal quality standard required for completed work. It creates a shared understanding of what it means for an Increment to be usable and complete. The Sprint Backlog describes current Sprint work, the Product Goal describes a future product state, and the Increment represents the resulting product work. Without a clear Definition of Done, different people could have conflicting interpretations of completion. Applying the same standard consistently improves transparency and ensures that work presented as completed meets the required quality expectations.
Question 75
Who creates the initial Sprint Backlog plan?
- Developers
- Product Owner
- Scrum Master
- Customer representative
Correct Answer: 1
Explanation:
Developers create the initial plan for delivering the Increment and record that plan in the Sprint Backlog. During Sprint Planning, they select Product Backlog items in collaboration with the Product Owner and determine how the work can be accomplished. Because Developers perform the work, they are best positioned to establish the implementation approach. The Product Owner provides product context and helps clarify value, while the Scrum Master facilitates understanding of Scrum. The plan is not permanently fixed; Developers continue adapting the Sprint Backlog as their understanding of the work develops during the Sprint.
Question 76
Which event has a maximum timebox of eight hours for one month?
- Sprint Retrospective
- Sprint Planning
- Sprint Review
- Daily Scrum
Correct Answer: 2
Explanation:
Sprint Planning has a maximum timebox of eight hours for a one-month Sprint. Its purpose is to establish the Sprint Goal, select work that can contribute toward that goal, and create an initial plan for delivering the Increment. The Sprint Review has a maximum of four hours for a one-month Sprint, while the Sprint Retrospective has a maximum of three hours. The Daily Scrum is limited to 15 minutes. These timeboxes help keep Scrum events focused and predictable. Shorter Sprints generally use shorter event durations where appropriate.
Question 77
What happens when the Product Goal is achieved?
- Another Product Goal is selected
- The Scrum Team permanently disbands
- Every Product Backlog item is deleted
- All Scrum events become optional
Correct Answer: 1
Explanation:
Once a Product Goal has been fulfilled or abandoned, the Scrum Team should take on the next Product Goal. The Product Goal provides a longer-term target for product development, so completing it creates an opportunity to establish a new meaningful direction. Achieving a Product Goal does not automatically mean the Scrum Team disbands or that all Product Backlog items disappear. Scrum events also remain part of the framework. The next Product Goal provides continuity and helps the team continue delivering value through subsequent Sprints and product improvements.
Question 78
Which statement describes the Sprint Backlog correctly?
- It is controlled exclusively by stakeholders
- It remains unchanged throughout the Sprint
- It is a plan created and adapted by Developers
- It replaces the Product Backlog permanently
Correct Answer: 3
Explanation:
The Sprint Backlog is a plan created by and for Developers. It includes the Sprint Goal, selected Product Backlog items, and an actionable plan for delivering the Increment. Because the plan is based on current understanding, it can change as Developers learn more during the Sprint. Stakeholders do not exclusively control it, and it does not replace the Product Backlog. The evolving nature of the Sprint Backlog supports empiricism by allowing Developers to respond to newly discovered information while maintaining the Sprint Goal as the objective.
Question 79
What does Courage help Scrum Team members do?
- Avoid difficult conversations
- Challenge assumptions when necessary
- Hide emerging risks
- Preserve outdated plans
Correct Answer: 2
Explanation:
Courage enables Scrum Team members to address difficult situations and do the right thing when circumstances require it. In complex product development, people may need to challenge assumptions, expose problems, discuss risks, or make uncomfortable decisions. Avoiding difficult conversations can reduce transparency and prevent useful adaptation. Similarly, hiding risks or preserving outdated plans can make empirical decision-making harder. Courage works with Openness, Respect, Focus, and Commitment to create effective Scrum behavior. It does not mean acting recklessly; rather, it supports constructive action when important issues need to be addressed.
Question 80
Why does Scrum use fixed-length Sprints?
- To create a predictable inspection cadence
- To eliminate every product risk
- To guarantee identical workload each cycle
- To prevent Product Backlog changes
Correct Answer: 1
Explanation:
Fixed-length Sprints create a regular cadence for producing an Increment and inspecting progress and outcomes. This predictable rhythm helps the Scrum Team and stakeholders establish recurring opportunities for inspection and adaptation. Sprints do not eliminate all product risks, guarantee identical workloads, or prevent Product Backlog changes. Instead, they provide a bounded period in which the team works toward a Sprint Goal while learning from actual results. A consistent Sprint cadence can make empirical product development easier to manage because everyone knows when important inspection and adaptation opportunities will occur.