Question 301
What is the primary purpose of a project charter?
- To provide detailed daily task assignments
- To authorize the project and define high-level objectives
- To document every project risk
- To establish the final lessons learned
Correct Answer: 2
Explanation
The project charter formally authorizes a project and provides a high-level description of its purpose, objectives, requirements, assumptions, constraints, major risks, milestones, and stakeholders. It also identifies the project manager and gives that person authority to use organizational resources for project activities. Detailed task assignments, comprehensive risk management, and lessons learned are developed or maintained during later project activities. The charter creates a common understanding of why the project exists and what it is expected to accomplish. Therefore, authorizing the project and defining its high-level objectives is its primary purpose.
Question 302
A project manager needs to determine which stakeholders require the most attention. Which factor should be considered?
- Their influence and interest
- Their job title only
- Their physical location
- The number of meetings they attend
Correct Answer: 1
Explanation
Stakeholder prioritization should consider factors such as power, influence, interest, impact, expectations, and potential support or resistance. Stakeholders with significant influence and strong interest generally require more active engagement because they can substantially affect project outcomes. A stakeholder’s job title alone does not determine the appropriate engagement strategy. Physical location and meeting attendance may affect communication methods but are not sufficient for prioritization. The project manager should continually assess stakeholder relationships because their influence and level of engagement can change as the project progresses.
Question 303
Which activity belongs to the Control Quality process?
- Creating the project charter
- Performing inspections and testing
- Developing the business case
- Identifying stakeholders
Correct Answer: 2
Explanation
Control Quality involves monitoring specific project results to determine whether they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results. Inspections, testing, and other quality control activities help verify that deliverables meet established requirements. Creating the charter and developing the business case occur during project initiation, while identifying stakeholders is an early project activity. Quality control provides objective information that can support formal acceptance and continuous improvement. Therefore, performing inspections and testing is an activity associated with Control Quality.
Question 304
A project team has identified a threat that cannot be eliminated but whose probability can be reduced. Which response is most appropriate?
- Avoid
- Transfer
- Mitigate
- Exploit
Correct Answer: 3
Explanation
Risk mitigation involves taking action to reduce the probability of a threat occurring or reduce its potential impact if it occurs. For example, additional testing, preventive maintenance, training, or using more reliable components may reduce exposure to a threat. Risk avoidance attempts to eliminate the threat or its cause entirely. Risk transfer shifts ownership or financial impact to a third party, while exploit is a response used for opportunities rather than threats. Since the threat cannot be eliminated but its probability can be reduced, mitigation is the appropriate response.
Question 305
A team is uncertain about how a new product feature will perform. What is a good agile approach for reducing uncertainty?
- Wait until project completion
- Deliver a small increment and gather feedback
- Avoid stakeholder involvement
- Freeze the backlog permanently
Correct Answer: 2
Explanation
Agile approaches reduce uncertainty by delivering small increments of value, obtaining feedback, and adapting based on what is learned. When a feature is uncertain, the team can create a manageable increment or experiment, demonstrate the result, and use stakeholder or customer feedback to guide future decisions. Waiting until completion delays learning and may increase rework. Avoiding stakeholders removes valuable information, while permanently freezing the backlog prevents adaptation. Therefore, delivering a small increment and gathering feedback is an effective way to reduce uncertainty.
Question 306
Which document records identified risks, their causes, responses, and owners?
- Risk register
- Issue log
- Stakeholder register
- Project charter
Correct Answer: 1
Explanation
The risk register is used to record identified individual project risks and important information about them. Depending on the project’s approach, it may include risk causes, descriptions, probability, impact, priority, response strategies, owners, triggers, and status. An issue log records problems that have already occurred and require action. The stakeholder register contains stakeholder information, while the project charter provides high-level authorization and project information. Maintaining an updated risk register helps the project team monitor uncertainty and implement appropriate responses throughout the project.
Question 307
A project manager wants to determine whether actual progress is faster or slower than planned. Which metric should be reviewed?
- CPI
- CV
- SPI
- EAC
Correct Answer: 3
Explanation
The Schedule Performance Index (SPI) measures schedule efficiency by comparing Earned Value (EV) with Planned Value (PV). It is calculated as SPI = EV ÷ PV. An SPI greater than 1.0 generally indicates that more value has been earned than planned, while an SPI below 1.0 indicates that less value has been earned than planned. CPI and CV focus on cost performance, while EAC forecasts the expected total project cost. Therefore, SPI is the appropriate metric for evaluating whether progress is faster or slower than planned.
Question 308
A project manager discovers that a customer is dissatisfied with a completed deliverable. What should the project manager review first?
- Acceptance criteria
- Team vacation schedule
- Resource histogram
- Procurement budget
Correct Answer: 1
Explanation
Acceptance criteria define the conditions a deliverable must meet to be accepted by the customer or other authorized stakeholder. When dissatisfaction occurs, the project manager should review the agreed acceptance criteria and compare them with the delivered result. This helps determine whether the deliverable actually fails to meet requirements or whether expectations have changed or were misunderstood. Other documents may become relevant later, but they do not directly establish whether the deliverable satisfies agreed acceptance conditions. Reviewing acceptance criteria therefore provides a logical starting point for resolving the concern.
Question 309
Which action best supports continuous improvement in an agile team?
- Avoiding feedback
- Conducting regular retrospectives
- Increasing documentation only
- Preventing process changes
Correct Answer: 2
Explanation
Regular retrospectives provide agile teams with an opportunity to inspect their ways of working and identify improvements. Team members can discuss what went well, what created difficulties, and what experiments or changes could improve future work. Continuous improvement depends on transparency, reflection, and willingness to adapt. Avoiding feedback or preventing process changes contradicts this principle. Although documentation may be valuable, simply increasing documentation does not guarantee process improvement. Therefore, conducting regular retrospectives is one of the most effective practices for supporting continuous improvement.
Question 310
A project manager must decide whether a proposed change will increase project risk. What should be done?
- Implement the change immediately
- Analyze the change’s potential impacts
- Reject every change
- Ask the team to decide without analysis
Correct Answer: 2
Explanation
A proposed change should be analyzed before implementation to understand its effects on scope, schedule, cost, quality, resources, risks, stakeholders, and benefits. This analysis provides decision-makers with sufficient information to determine whether the change supports project objectives and whether additional responses are required. Automatically implementing changes can create uncontrolled impacts, while automatically rejecting changes may prevent valuable improvements. The project manager should use the established change control process and provide objective impact information to the appropriate decision-making authority.
Question 311
What does a negative Schedule Variance indicate?
- The project is ahead of schedule
- The project is exactly on schedule
- The project has favorable cost performance
- The project is behind the planned schedule
Correct Answer: 4
Explanation
Schedule Variance (SV) is calculated as Earned Value (EV) minus Planned Value (PV). A negative SV indicates that the earned value is less than the planned value, meaning less work has been accomplished than planned at the measurement point. This generally indicates unfavorable schedule performance. A positive SV indicates favorable schedule performance, while cost performance is evaluated using measures such as CV and CPI. Therefore, a negative Schedule Variance indicates that the project is behind the planned schedule based on earned value analysis.
Question 312
A project manager wants to identify stakeholders who may resist a major organizational change. What should the manager do?
- Analyze stakeholder attitudes and influence
- Remove resistant stakeholders
- Ignore resistance
- Delay all communication
Correct Answer: 1
Explanation
Stakeholder analysis helps the project manager understand stakeholders’ interests, influence, expectations, attitudes, and potential reactions to project changes. Identifying likely resistance early allows the manager to develop targeted engagement, communication, training, and support strategies. Removing or ignoring resistant stakeholders may increase opposition and create additional project risks. Delaying communication can also allow misinformation to spread. The project manager should understand the reasons for resistance and address legitimate concerns while maintaining alignment with project objectives. Therefore, analyzing stakeholder attitudes and influence is the appropriate approach.
Question 313
Which contract type places the greatest cost risk on the buyer?
- Firm-fixed-price
- Fixed-price-incentive
- Cost-reimbursable
- Fixed-price
Correct Answer: 3
Explanation
Cost-reimbursable contracts generally place greater cost risk on the buyer because the buyer pays the seller for allowable costs incurred, subject to the specific contract terms. The final amount may vary depending on the actual cost of performing the work. In a firm-fixed-price contract, the seller generally assumes greater cost risk because the agreed price remains fixed unless contract changes occur. Understanding risk allocation is important when selecting contract types. Therefore, among the listed options, a cost-reimbursable contract generally places the greatest cost risk on the buyer.
Question 314
A project team needs to estimate the cost of a large deliverable by estimating each smaller component and then adding them together. Which technique is being used?
- Analogous estimating
- Bottom-up estimating
- Parametric estimating
- Expert judgment
Correct Answer: 2
Explanation
Bottom-up estimating develops estimates for detailed components of work and then aggregates those estimates to determine the overall estimate. It can provide greater accuracy because the team examines the actual work required at a lower level of detail. However, it can require more time and effort than high-level estimating techniques. Analogous estimating relies on historical information from similar projects, while parametric estimating uses statistical relationships between variables. Expert judgment relies on specialized knowledge and experience. Therefore, estimating smaller components and aggregating them describes bottom-up estimating.
Question 315
A team member repeatedly misses commitments because the workload is unrealistic. What should the project manager do first?
- Publicly criticize the team member
- Remove the team member
- Discuss the workload and identify a workable solution
- Escalate directly to senior management
Correct Answer: 3
Explanation
The project manager should first discuss the situation with the team member to understand the workload, constraints, dependencies, and reasons commitments are being missed. If the workload is unrealistic, the manager can explore options such as reprioritizing work, reallocating tasks, adjusting commitments, or obtaining additional support. Public criticism can damage trust, while removing or escalating the team member may be premature. Constructive communication helps identify the actual cause and supports a solution that improves both individual and team performance.
Question 316
Which agile metric shows the amount of work remaining over time?
- Burndown chart
- RACI matrix
- Risk matrix
- Stakeholder map
Correct Answer: 1
Explanation
A burndown chart shows the amount of work remaining over time and can help an agile team visualize progress toward completing a sprint or other body of work. As work is completed, the remaining amount should generally decrease. The chart can help identify whether the team is likely to achieve its target and can stimulate discussion when progress differs significantly from expectations. A RACI matrix clarifies responsibilities, a risk matrix analyzes risks, and a stakeholder map examines stakeholder relationships. Therefore, a burndown chart is the appropriate metric.
Question 317
A project manager identifies a possible positive event that could significantly benefit the project. Which risk response could ensure the opportunity occurs?
- Avoid
- Exploit
- Mitigate
- Transfer
Correct Answer: 2
Explanation
Exploit is a risk response strategy used for opportunities. It involves taking action to ensure that the opportunity occurs and its potential benefit is realized. For example, a project may assign its most capable resources to an opportunity that could accelerate delivery or provide additional value. Avoid is generally used for threats, while mitigate reduces the probability or impact of a threat or sometimes enhances an opportunity without guaranteeing it. Transfer is commonly used to shift ownership of a threat or opportunity to another party. Therefore, exploit is correct.
Question 318
What is the purpose of a resource calendar?
- To record stakeholder complaints
- To identify when resources are available
- To define product acceptance criteria
- To calculate project profit
Correct Answer: 2
Explanation
A resource calendar identifies the periods when specific project resources are available for planned work. It may include information about team members, equipment, facilities, or other resources and can account for holidays, vacations, shifts, maintenance periods, and other availability constraints. This information helps the project manager develop realistic schedules and allocate resources effectively. A resource calendar does not define acceptance criteria, record stakeholder complaints, or calculate project profit. Therefore, identifying when resources are available is its primary purpose.
Question 319
A project manager wants to ensure that only approved work is included in the project. Which practice is most important?
- Uncontrolled scope expansion
- Formal scope control
- Informal requirement additions
- Delaying stakeholder reviews
Correct Answer: 2
Explanation
Formal scope control helps ensure that project work remains aligned with the approved scope baseline and that proposed changes are evaluated through the appropriate change control process. Without effective scope control, stakeholders may add requirements informally, leading to scope creep, schedule delays, cost increases, and resource problems. The project manager should monitor scope performance, assess requested changes, and ensure that approved changes are incorporated properly. Therefore, formal scope control is essential for ensuring that only authorized project work is included.
Question 320
A project is approaching completion, and the customer has accepted all major deliverables. What should the project manager do next?
- Start unrelated project work
- Release all resources without documentation
- Complete formal closure and transition activities
- Reopen completed requirements
Correct Answer: 3
Explanation
After major deliverables are accepted, the project manager should complete formal closure activities. These may include confirming final acceptance, completing contractual and administrative requirements, archiving project records, capturing lessons learned, obtaining appropriate closure approvals, releasing resources, and transitioning products or services to operations or the responsible owner. Simply releasing resources without documentation can leave important obligations incomplete. Reopening completed requirements is unnecessary unless an approved change exists. Formal closure ensures the project is properly completed and organizational knowledge is preserved.