Pass PMI CAPM Exam in First Attempt Easily
Real PMI CAPM Exam Questions, Accurate & Verified Answers As Experienced in the Actual Test!

Verified by experts
3 products

You save $69.98

CAPM Premium Bundle

  • Premium File 688 Questions & Answers
  • Last Update: Nov 11, 2026
  • Training Course 123 Lectures
  • Study Guide 719 Pages
$79.99 $149.97

Purchase Individually

  • Premium File

    688 Questions & Answers
    Last Update: Nov 11, 2026

    $76.99
    $69.99
  • Training Course

    123 Lectures

    $43.99
    $39.99
  • Study Guide

    719 Pages

    $43.99
    $39.99

Certified Associate in Project Management (PMI-100) CAPM Practice Test 24

Question 230

The project or product decision does not produce its expected result. A government procurement has a fixed deliverable and formal contract, but the new project manager assumes all technical staff report directly to them despite a weak matrix structure. Which investigation should be prioritized to diagnose the problem?

  1. Inspect WBS dictionary, activity list, dependency logic and resource estimates.
  2. Inspect organizational chart, resource commitments, contracting roles and project authorization.
  3. Inspect scope statement, acceptance list, WBS work packages and decomposition logic.
  4. Inspect EV and PV source definitions, status date, work completion evidence and baseline version.

Explanation

Correct Answer

B:

Inspect organizational chart, resource commitments, contracting roles and project authorization. These are the relevant initial evidence checks for Using organizational structure in a fixed defense procurement project. Intended action: Plan specialist staffing and approvals through functional managers while maintaining an integrated predictive deliverable schedule. Expected success condition: The procurement plan has confirmed functional resource commitments and compliant approval pathways.

Incorrect Answers

A:

Inspect WBS dictionary, activity list, dependency logic and resource estimates. This investigation primarily applies to Separating a work package from a schedule activity, not the current Using organizational structure in a fixed defense procurement project problem. Prioritize: Inspect organizational chart, resource commitments, contracting roles and project authorization.

C:

Inspect scope statement, acceptance list, WBS work packages and decomposition logic. This investigation primarily applies to Building a WBS around deliverables rather than organization names, not the current Using organizational structure in a fixed defense procurement project problem. Prioritize: Inspect organizational chart, resource commitments, contracting roles and project authorization.

D:

Inspect EV and PV source definitions, status date, work completion evidence and baseline version. This investigation primarily applies to Calculating negative schedule variance with earned value data, not the current Using organizational structure in a fixed defense procurement project problem. Prioritize: Inspect organizational chart, resource commitments, contracting roles and project authorization.

Question 231

An associate project management team faces this situation: A bridge replacement team has approved drawings but no work package decomposition or WBS dictionary, and reports task progress solely against purchase orders. Which design or implementation action best addresses it?

  1. Apply the approved quality management plan with process checks, acceptance criteria and corrective action before subsequent pours.
  2. Establish a scope baseline with scope statement, WBS and relevant WBS dictionary descriptions aligned to the approved design.
  3. Record the permit lapse as an issue, assess schedule and cost impacts, and process any baseline change through approval.
  4. Calculate total float as LF minus EF, giving four days of allowed delay under the stated network constraints.

Explanation

Correct Answer

B:

Establish a scope baseline with scope statement, WBS and relevant WBS dictionary descriptions aligned to the approved design. Technical reason: A predictive scope baseline decomposes authorized deliverables into controlled planning and measurement components. Verify by: Construction progress is mapped to defined deliverables and authorized work packages rather than only supplier invoices. Deployment qualification: A WBS organizes deliverable scope; individual schedule activities provide the duration and sequencing detail.

Incorrect Answers

A:

Apply the approved quality management plan with process checks, acceptance criteria and corrective action before subsequent pours. This instead targets the different case Using a quality management plan to prevent recurring paving defects. The described Distinguishing scope baseline components in a public bridge replacement requirement specifically calls for Establish a scope baseline with scope statement, WBS and relevant WBS dictionary descriptions aligned to the approved design.

C:

Record the permit lapse as an issue, assess schedule and cost impacts, and process any baseline change through approval. This instead targets the different case Maintaining a change and issue log after unexpected permit delay. The described Distinguishing scope baseline components in a public bridge replacement requirement specifically calls for Establish a scope baseline with scope statement, WBS and relevant WBS dictionary descriptions aligned to the approved design.

D:

Calculate total float as LF minus EF, giving four days of allowed delay under the stated network constraints. This instead targets the different case Calculating float for a noncritical data conversion task. The described Distinguishing scope baseline components in a public bridge replacement requirement specifically calls for Establish a scope baseline with scope statement, WBS and relevant WBS dictionary descriptions aligned to the approved design.

Question 232

During project acceptance review, the team must verify its proposed approach. A bridge replacement team has approved drawings but no work package decomposition or WBS dictionary, and reports task progress solely against purchase orders. Which observed result is the most direct acceptance evidence?

  1. Construction progress is mapped to defined deliverables and authorized work packages rather than only supplier invoices.
  2. The payment decision traces to passed verification steps and the authorized acceptance signature.
  3. The schedule accounts for translation, review and deployment while retaining the deliverable work package in the WBS.
  4. The cost comparison shows testing at $2,000 per day against shipment at $7,000 per day with monitored path impacts.

Explanation

Correct Answer

A:

Construction progress is mapped to defined deliverables and authorized work packages rather than only supplier invoices. Recommended implementation: Establish a scope baseline with scope statement, WBS and relevant WBS dictionary descriptions aligned to the approved design. Why the observation matters: A predictive scope baseline decomposes authorized deliverables into controlled planning and measurement components.

Incorrect Answers

B:

The payment decision traces to passed verification steps and the authorized acceptance signature. That observation could confirm Controlling quality verification artifacts for a predictive supplier build, not the current Distinguishing scope baseline components in a public bridge replacement case. For this case, the decisive observation is: Construction progress is mapped to defined deliverables and authorized work packages rather than only supplier invoices.

C:

The schedule accounts for translation, review and deployment while retaining the deliverable work package in the WBS. That observation could confirm Separating a work package from a schedule activity, not the current Distinguishing scope baseline components in a public bridge replacement case. For this case, the decisive observation is: Construction progress is mapped to defined deliverables and authorized work packages rather than only supplier invoices.

D:

The cost comparison shows testing at $2,000 per day against shipment at $7,000 per day with monitored path impacts. That observation could confirm Estimating crashing costs for two critical path alternatives, not the current Distinguishing scope baseline components in a public bridge replacement case. For this case, the decisive observation is: Construction progress is mapped to defined deliverables and authorized work packages rather than only supplier invoices.

Question 233

An associate project coordinator explains why the response works. A bridge replacement team has approved drawings but no work package decomposition or WBS dictionary, and reports task progress solely against purchase orders. Which principle is most relevant to this case?

  1. Predictive project controls use defined artifacts to substantiate progress, quality and contractual completion.
  2. Quality assurance and quality control combine prevention-focused processes and verification of resulting outputs.
  3. A predictive scope baseline decomposes authorized deliverables into controlled planning and measurement components.
  4. Total float measures how long an activity can slip without changing the defined project finish under current logic.

Explanation

Correct Answer

C:

A predictive scope baseline decomposes authorized deliverables into controlled planning and measurement components. This mechanism explains Distinguishing scope baseline components in a public bridge replacement. Action: Establish a scope baseline with scope statement, WBS and relevant WBS dictionary descriptions aligned to the approved design. Expected confirmation: Construction progress is mapped to defined deliverables and authorized work packages rather than only supplier invoices.

Incorrect Answers

A:

Predictive project controls use defined artifacts to substantiate progress, quality and contractual completion. This relates to Controlling quality verification artifacts for a predictive supplier build. In the current Distinguishing scope baseline components in a public bridge replacement case the operative principle is: A predictive scope baseline decomposes authorized deliverables into controlled planning and measurement components.

B:

Quality assurance and quality control combine prevention-focused processes and verification of resulting outputs. This relates to Using a quality management plan to prevent recurring paving defects. In the current Distinguishing scope baseline components in a public bridge replacement case the operative principle is: A predictive scope baseline decomposes authorized deliverables into controlled planning and measurement components.

D:

Total float measures how long an activity can slip without changing the defined project finish under current logic. This relates to Calculating float for a noncritical data conversion task. In the current Distinguishing scope baseline components in a public bridge replacement case the operative principle is: A predictive scope baseline decomposes authorized deliverables into controlled planning and measurement components.

Question 234

The project team omits the necessary planned action or control. A bridge replacement team has approved drawings but no work package decomposition or WBS dictionary, and reports task progress solely against purchase orders. Which resulting failure or risk is most directly relevant?

  1. Choosing costlier ineffective compression can consume contingency without recovering the completion date.
  2. One undifferentiated red flag can prompt the wrong corrective action or conceal an unfavorable cost trend.
  3. Independent function schedules can conceal incompatible dates and create a ceremonial launch before actual readiness.
  4. Without decomposition the team can miss required inspection or commissioning work even while spending stays visible.

Explanation

Correct Answer

D:

Without decomposition the team can miss required inspection or commissioning work even while spending stays visible. This is the direct exposure for Distinguishing scope baseline components in a public bridge replacement. Mitigate with: Establish a scope baseline with scope statement, WBS and relevant WBS dictionary descriptions aligned to the approved design. Check success by: Construction progress is mapped to defined deliverables and authorized work packages rather than only supplier invoices.

Incorrect Answers

A:

Choosing costlier ineffective compression can consume contingency without recovering the completion date. This risk occurs in the different Estimating crashing costs for two critical path alternatives situation. For the given Distinguishing scope baseline components in a public bridge replacement requirement, the directly relevant risk is: Without decomposition the team can miss required inspection or commissioning work even while spending stays visible.

B:

One undifferentiated red flag can prompt the wrong corrective action or conceal an unfavorable cost trend. This risk occurs in the different Using a variance report to distinguish delay from cost overrun situation. For the given Distinguishing scope baseline components in a public bridge replacement requirement, the directly relevant risk is: Without decomposition the team can miss required inspection or commissioning work even while spending stays visible.

C:

Independent function schedules can conceal incompatible dates and create a ceremonial launch before actual readiness. This risk occurs in the different Coordinating an integrated plan for a museum exhibit opening situation. For the given Distinguishing scope baseline components in a public bridge replacement requirement, the directly relevant risk is: Without decomposition the team can miss required inspection or commissioning work even while spending stays visible.

Question 235

The project or product decision does not produce its expected result. A bridge replacement team has approved drawings but no work package decomposition or WBS dictionary, and reports task progress solely against purchase orders. Which investigation should be prioritized to diagnose the problem?

  1. Inspect WBS dictionary, activity list, dependency logic and resource estimates.
  2. Inspect dependency types, lead allowances, procurement commitment point and change exposure.
  3. Inspect permit expiry, issue register, impact analysis, change log and revised schedule approvals.
  4. Inspect WBS hierarchy, scope statement, work package descriptions and control account assignments.

Explanation

Correct Answer

D:

Inspect WBS hierarchy, scope statement, work package descriptions and control account assignments. These are the relevant initial evidence checks for Distinguishing scope baseline components in a public bridge replacement. Intended action: Establish a scope baseline with scope statement, WBS and relevant WBS dictionary descriptions aligned to the approved design. Expected success condition: Construction progress is mapped to defined deliverables and authorized work packages rather than only supplier invoices.

Incorrect Answers

A:

Inspect WBS dictionary, activity list, dependency logic and resource estimates. This investigation primarily applies to Separating a work package from a schedule activity, not the current Distinguishing scope baseline components in a public bridge replacement problem. Prioritize: Inspect WBS hierarchy, scope statement, work package descriptions and control account assignments.

B:

Inspect dependency types, lead allowances, procurement commitment point and change exposure. This investigation primarily applies to Estimating schedule effect of fast tracking overlapping reviews, not the current Distinguishing scope baseline components in a public bridge replacement problem. Prioritize: Inspect WBS hierarchy, scope statement, work package descriptions and control account assignments.

C:

Inspect permit expiry, issue register, impact analysis, change log and revised schedule approvals. This investigation primarily applies to Maintaining a change and issue log after unexpected permit delay, not the current Distinguishing scope baseline components in a public bridge replacement problem. Prioritize: Inspect WBS hierarchy, scope statement, work package descriptions and control account assignments.

Question 236

An associate project management team faces this situation: A solar farm interconnection plan has approved technical requirements but engineers want to bypass the design review and start construction to gain two weeks. Which design or implementation action best addresses it?

  1. Require the contractually specified inspection evidence and formal acceptance record before approving the milestone payment.
  2. Retain the planned design and safety review stage gate and obtain evidence-based authorization before commencing downstream work.
  3. Create a deliverable-oriented WBS that captures the full authorized scope including rollout and training components.
  4. Calculate total float as LF minus EF, giving four days of allowed delay under the stated network constraints.

Explanation

Correct Answer

B:

Retain the planned design and safety review stage gate and obtain evidence-based authorization before commencing downstream work. Technical reason: Stage gates provide management decisions between phases where stable deliverables must satisfy defined entry conditions. Verify by: Construction starts after documented approval of the necessary electrical and environmental readiness criteria. Deployment qualification: Some overlap or fast tracking may be possible only after risks and approval authority are explicitly assessed.

Incorrect Answers

A:

Require the contractually specified inspection evidence and formal acceptance record before approving the milestone payment. This instead targets the different case Controlling quality verification artifacts for a predictive supplier build. The described Planning fixed deliverable reviews through stage gates requirement specifically calls for Retain the planned design and safety review stage gate and obtain evidence-based authorization before commencing downstream work.

C:

Create a deliverable-oriented WBS that captures the full authorized scope including rollout and training components. This instead targets the different case Building a WBS around deliverables rather than organization names. The described Planning fixed deliverable reviews through stage gates requirement specifically calls for Retain the planned design and safety review stage gate and obtain evidence-based authorization before commencing downstream work.

D:

Calculate total float as LF minus EF, giving four days of allowed delay under the stated network constraints. This instead targets the different case Calculating float for a noncritical data conversion task. The described Planning fixed deliverable reviews through stage gates requirement specifically calls for Retain the planned design and safety review stage gate and obtain evidence-based authorization before commencing downstream work.

Question 237

During project acceptance review, the team must verify its proposed approach. A solar farm interconnection plan has approved technical requirements but engineers want to bypass the design review and start construction to gain two weeks. Which observed result is the most direct acceptance evidence?

  1. Construction starts after documented approval of the necessary electrical and environmental readiness criteria.
  2. The press opening milestone is driven by the required artwork, safety and security readiness predecessors.
  3. The schedule accounts for translation, review and deployment while retaining the deliverable work package in the WBS.
  4. The network model reports 13 days for A-B-D versus 9 days for A-C-D under the stated finish-to-start assumptions.

Explanation

Correct Answer

A:

Construction starts after documented approval of the necessary electrical and environmental readiness criteria. Recommended implementation: Retain the planned design and safety review stage gate and obtain evidence-based authorization before commencing downstream work. Why the observation matters: Stage gates provide management decisions between phases where stable deliverables must satisfy defined entry conditions.

Incorrect Answers

B:

The press opening milestone is driven by the required artwork, safety and security readiness predecessors. That observation could confirm Coordinating an integrated plan for a museum exhibit opening, not the current Planning fixed deliverable reviews through stage gates case. For this case, the decisive observation is: Construction starts after documented approval of the necessary electrical and environmental readiness criteria.

C:

The schedule accounts for translation, review and deployment while retaining the deliverable work package in the WBS. That observation could confirm Separating a work package from a schedule activity, not the current Planning fixed deliverable reviews through stage gates case. For this case, the decisive observation is: Construction starts after documented approval of the necessary electrical and environmental readiness criteria.

D:

The network model reports 13 days for A-B-D versus 9 days for A-C-D under the stated finish-to-start assumptions. That observation could confirm Calculating the critical path of a campus network upgrade, not the current Planning fixed deliverable reviews through stage gates case. For this case, the decisive observation is: Construction starts after documented approval of the necessary electrical and environmental readiness criteria.

Question 238

An associate project coordinator explains why the response works. A solar farm interconnection plan has approved technical requirements but engineers want to bypass the design review and start construction to gain two weeks. Which principle is most relevant to this case?

  1. Schedule and cost variances use different comparators and support different management investigations.
  2. Stage gates provide management decisions between phases where stable deliverables must satisfy defined entry conditions.
  3. Total float measures how long an activity can slip without changing the defined project finish under current logic.
  4. The critical path is the longest-duration logical path through a properly linked deterministic schedule network.

Explanation

Correct Answer

B:

Stage gates provide management decisions between phases where stable deliverables must satisfy defined entry conditions. This mechanism explains Planning fixed deliverable reviews through stage gates. Action: Retain the planned design and safety review stage gate and obtain evidence-based authorization before commencing downstream work. Expected confirmation: Construction starts after documented approval of the necessary electrical and environmental readiness criteria.

Incorrect Answers

A:

Schedule and cost variances use different comparators and support different management investigations. This relates to Using a variance report to distinguish delay from cost overrun. In the current Planning fixed deliverable reviews through stage gates case the operative principle is: Stage gates provide management decisions between phases where stable deliverables must satisfy defined entry conditions.

C:

Total float measures how long an activity can slip without changing the defined project finish under current logic. This relates to Calculating float for a noncritical data conversion task. In the current Planning fixed deliverable reviews through stage gates case the operative principle is: Stage gates provide management decisions between phases where stable deliverables must satisfy defined entry conditions.

D:

The critical path is the longest-duration logical path through a properly linked deterministic schedule network. This relates to Calculating the critical path of a campus network upgrade. In the current Planning fixed deliverable reviews through stage gates case the operative principle is: Stage gates provide management decisions between phases where stable deliverables must satisfy defined entry conditions.

Question 239

The project team omits the necessary planned action or control. A solar farm interconnection plan has approved technical requirements but engineers want to bypass the design review and start construction to gain two weeks. Which resulting failure or risk is most directly relevant?

  1. Concealed permit problems can cause compliance violations and misleading schedule reports.
  2. Interpreting a ratio as elapsed days can misinform milestone risk and executive decisions.
  3. Bypassing review can create rework and safety exposure that outweighs apparent schedule savings.
  4. One undifferentiated red flag can prompt the wrong corrective action or conceal an unfavorable cost trend.

Explanation

Correct Answer

C:

Bypassing review can create rework and safety exposure that outweighs apparent schedule savings. This is the direct exposure for Planning fixed deliverable reviews through stage gates. Mitigate with: Retain the planned design and safety review stage gate and obtain evidence-based authorization before commencing downstream work. Check success by: Construction starts after documented approval of the necessary electrical and environmental readiness criteria.

Incorrect Answers

A:

Concealed permit problems can cause compliance violations and misleading schedule reports. This risk occurs in the different Maintaining a change and issue log after unexpected permit delay situation. For the given Planning fixed deliverable reviews through stage gates requirement, the directly relevant risk is: Bypassing review can create rework and safety exposure that outweighs apparent schedule savings.

B:

Interpreting a ratio as elapsed days can misinform milestone risk and executive decisions. This risk occurs in the different Explaining positive schedule performance index versus schedule variance situation. For the given Planning fixed deliverable reviews through stage gates requirement, the directly relevant risk is: Bypassing review can create rework and safety exposure that outweighs apparent schedule savings.

D:

One undifferentiated red flag can prompt the wrong corrective action or conceal an unfavorable cost trend. This risk occurs in the different Using a variance report to distinguish delay from cost overrun situation. For the given Planning fixed deliverable reviews through stage gates requirement, the directly relevant risk is: Bypassing review can create rework and safety exposure that outweighs apparent schedule savings.

Question 240

The project or product decision does not produce its expected result. A solar farm interconnection plan has approved technical requirements but engineers want to bypass the design review and start construction to gain two weeks. Which investigation should be prioritized to diagnose the problem?

  1. Inspect gate checklist, drawings, risk findings, authority signatures and planned follow-on tasks.
  2. Inspect integrated master schedule, critical handoffs, vendor dates and gate ownership.
  3. Inspect scope statement, acceptance list, WBS work packages and decomposition logic.
  4. Inspect EV and PV source definitions, status date, work completion evidence and baseline version.

Explanation

Correct Answer

A:

Inspect gate checklist, drawings, risk findings, authority signatures and planned follow-on tasks. These are the relevant initial evidence checks for Planning fixed deliverable reviews through stage gates. Intended action: Retain the planned design and safety review stage gate and obtain evidence-based authorization before commencing downstream work. Expected success condition: Construction starts after documented approval of the necessary electrical and environmental readiness criteria.

Incorrect Answers

B:

Inspect integrated master schedule, critical handoffs, vendor dates and gate ownership. This investigation primarily applies to Coordinating an integrated plan for a museum exhibit opening, not the current Planning fixed deliverable reviews through stage gates problem. Prioritize: Inspect gate checklist, drawings, risk findings, authority signatures and planned follow-on tasks.

C:

Inspect scope statement, acceptance list, WBS work packages and decomposition logic. This investigation primarily applies to Building a WBS around deliverables rather than organization names, not the current Planning fixed deliverable reviews through stage gates problem. Prioritize: Inspect gate checklist, drawings, risk findings, authority signatures and planned follow-on tasks.

D:

Inspect EV and PV source definitions, status date, work completion evidence and baseline version. This investigation primarily applies to Calculating negative schedule variance with earned value data, not the current Planning fixed deliverable reviews through stage gates problem. Prioritize: Inspect gate checklist, drawings, risk findings, authority signatures and planned follow-on tasks.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

Purchase Individually

  • Premium File

    688 Questions & Answers
    Last Update: Nov 11, 2026

    $76.99
    $69.99
  • Training Course

    123 Lectures

    $43.99
    $39.99
  • Study Guide

    719 Pages

    $43.99
    $39.99

SPECIAL OFFER: GET 10% OFF
This is ONE TIME OFFER

You save
10%

Enter Your Email Address to Receive Your 10% Off Discount Code

SPECIAL OFFER: GET 10% OFF

You save
10%

Use Discount Code:

A confirmation link was sent to your e-mail.

Please check your mailbox for a message from support@examlabs.com and follow the directions.

Download Free Demo of VCE Exam Simulator

Experience Avanset VCE Exam Simulator for yourself.

Simply submit your email address below to get started with our interactive software demo of your free trial.

  • Realistic exam simulation and exam editor with preview functions
  • Whole exam in a single file with several different question types
  • Customizable exam-taking mode & detailed score reports